Politicians eager, entrepreneurs doubtful about viability of small power plants
Although prospective entrepreneurs are doubtful about financial viability of small power plants, politicians are showing interest to the new venture.
bdnews24.com News Service
bdnews24.com
Published :
26 Apr 2005, 06:00 PM
Updated :
17 Aug 2022, 08:33 PM
Dhaka, April 27 (BDNEWS) – Although prospective entrepreneurs are doubtful about financial viability of small power plants, politicians are showing interest to the new venture.
The government's economic affairs committee on April 23 approved the new policy for setting up of 10-50 megawatt small power plants in the private sector.
Since the approval, officials concerned said, a number of prospective investors enquired from State Minister for Energy AKM Mosharraf Hossain and State Minister for Power Iqbal Hassan Mahmood about the new venture.
Most of them are politicians, including former and present MPs. Everyone wants to sell electricity to the government.
However, as per the policy, there is no guarantee from the government that it will purchase electricity from the small plants.
Due to the non-surety of the government to purchase power from the small plants, experts said, the programme is unlikely to be successful.
They also said the fixed rate is another reason that the entrepreneurs might not show interest.
Moazzem Hossain, vice president of Bangladesh Energy Companies Association, however, said investment is possible under the fixed rate of gas to be bought and electricity to be sold.
"But, for this the government will have to assure that it will purchase 60 percent of the electricity to be produced by a small plant," he told BDNEWS.
An official of the Power Division, preferring anonymity, called the new policy for small plants a bid to hide the government's failure in the sector in last three years.
"If the government wants success, it will have to give the guarantee to purchase the power from the small units," he said.
A former top official of Power Development Board (PDB) said the new policy sounds easy, but its implementation will be very tough.
Elaborating the reasons, he said, for procuring a licence for the plant from Bangladesh Energy Regulatory Commission (BERC), an entrepreneur at first has to sign a contract with a buyer.
"Also, the entrepreneur has to sign an agreement with the Petrobangla companies that supplies gas in the area where the plant will be set up. Besides, the entrepreneur has to get environmental impact clearance from the Department of Environment."
Considering the investment amount, experts in the sector said, the minimum tariff of per kilowatt/hour electricity should be 3.5 cents. But the government fixed it at 2.73 cents.
A German expert said cost of per kilowatt/hour electricity of a European standard 12megawatt plant will be 3.3 cents.
With the government suggested rate of gas for the small plants (US$ 1.2 or Tk 72.45 at which PDB gets gas from Petrobangla), the energy cost of per kilowatt/hour electricity will be 1.9 cents while capital expenditure 88 cents, operational and maintenance cost 44 cents and other costs 0.08 cents, he said.
Mosharraf Hossain, the acting chairman of BERC from where the entrepreneurs will get licences, said they are yet to officially know about the plan.
However, he said, the BERC has finalised the policy for providing licence for power generation.
"It will take six weeks to issue a licence after submission of an application fulfilling all conditions," Mosharraf Hossain told BDNEWS.
The application charge for per megawatt is Tk 5,000. The annual licence fee of a power plant up to 50 megawatt is Tk 500,000.
Under the policy, the entrepreneurs will get different tax and duty facilities.
However, experts said the small power plants will increase waste natural gas and called it a suicidal decision in this era of energy conservation and its skilled uses.
According to them, consumption of gas in a small plant is 150 percent higher than that of in a big plant.
A 450-megawatt plant consumes 70 to 75 million cubic feet of gas per day (MMCFD), but an 11-megawatt plant will need three MMCFD, the added.
BDNEWS/1843 hrs