LNG surge lifts grid: Regasified LNG output rebounds to 810mmcfd, driving total national gas supply up by 26 percent

Power sector prioritised: Gas allocation to power plants jumps 37 percent despite overall daily shortfalls against demand

Non-Power sectors squeezed: Supply to industrial, commercial, and domestic users falls 44 percent to cushion grid deficits

Gas supply to the national grid has climbed 26 percent, driven by a rise in output from floating LNG terminals, though the shortfall against demand remains steep.

Tariqul Islam, deputy general manager of Petrobangla's public relations wing, said gas supply to the national grid stood at 2,425 million cubic feet per day (mmcfd) as of 4pm on Saturday. 

Of this, 1,615mmcfd came from domestic gas fields, while 810mmcfd came from regasified imported LNG.

A day earlier, Petrobangla's daily report for the 24 hours to 8am Friday put total supply at 1,931.2mmcfd. 

That means supply has risen by 493.8mmcfd, or roughly 26 percent, by Saturday afternoon.

LNG supply stood at 300.2mmcfd in the Thursday-Friday period, climbing to 810mmcfd by Saturday afternoon. 

Domestic gas production, meanwhile, slipped slightly over the same period, from 1,631mmcfd to 1,615mmcfd.

The overall rise in gas supply, in other words, has come from the jump in LNG output.

As of 4pm Saturday, Moheshkhali's Excelerate LNG terminal was supplying 300mmcfd, while the Summit LNG terminal was supplying 510mmcfd.

LNG Down 60% Over 5 Days

Petrobangla's five most recent daily production and distribution reports show LNG supply stood at 749mmcfd in the 24 hours to 8am on Aug 9. 

By the 24 hours to 8am on Aug 13, that had fallen to 300.2mmcfd.

LNG supply, in other words, fell by 448.8mmcfd, or nearly 60 percent, over five days, dragging down total gas supply along with it.

Total gas supply stood at 2,374.9mmcfd on Aug 9-10, falling to 1,931.2mmcfd by Aug 13-14, a drop of around 19 percent.

Domestic gas field output changed little over the five-day span, ranging between 1,626mmcfd and 1,642mmcfd. 

As a result, the shortfall from falling LNG supply could not be offset from domestic sources.

Power Plants Get Bigger Share

Even as total gas supply fell, the share reaching gas-fired power plants rose. Power plants received 694mmcfd on Aug 9-10, climbing to 953.1mmcfd by Aug 13-14, a rise of around 37 percent over five days.

Despite the increase, supply still fell short of demand. Petrobangla's report puts daily demand from the power sector at 2,524.9mmcfd, meaning power plants received less than 38 percent of their requirement as of Aug 13-14.

Gas supply to fertiliser factories rose from 124.5mmcfd to 140.9mmcfd, covering around 43 percent of daily demand of 329mmcfd by the final day.

The steepest fall came in the "other" category, covering sectors outside power and fertiliser. 

Supply here stood at 1,520.8mmcfd on Aug 9-10, dropping to 855.5mmcfd by Aug 13-14, a fall of 665.3mmcfd, or roughly 44 percent, over five days.

Petrobangla's report does not break down this "other" category further, so it remains unclear how much of the drop hit industrial, residential, commercial or CNG users specifically.

Cox's Bazar's Moheshkhali hosts two floating LNG terminals, one operated by Excelerate Energy and the other by Summit LNG, with daily regasification capacities of 600mmcfd and 500mmcfd respectively.

Combined, the two terminals are currently supplying 760mmcfd.

A fire at the MLNG (Excelerate) terminal on Jul 21 kept it shut for more than two weeks before one of its units was partially restored, though it has yet to return to full capacity.

The Summit terminal's own shutdown over the past two days deepened the gas crunch further, straining supply to power plants, factories, CNG stations and households.

Bangladesh's daily gas demand stands at around 3,800 to 4,000mmcfd. Even under normal circumstances, combined domestic gas and imported LNG supply to the national grid runs at around 2,600mmcfd.

The crisis has deepened further as long-term LNG supply from Qatar has been disrupted amid the conflict in West Asia, forcing the government to turn to the spot market and direct purchases to plug the shortfall.