The project’s engineers said the span no. 7F was placed on the piers 41 and 42 at the Jazira end on Friday afternoon, also linking the other spans with the shore.
A floating crane carried the span from a specialised workshop jetty at Kumarbhog earlier in the morning.
The bridge will have a total of 41 of spans, each 150 metres long and weighing 3,140 tonnes.
The first span of the bridge was installed on Sept 30 of last year between pillars 37 and 38 on the Jazira side.The second was installed on Jan 28 between pillars 38 and 39, while the third was placed between pillars 39 and 40 on Mar 11.
The sixth span will be installed at the Mawa end of the 6.15-kilometre bridge.
The government is aiming to finish construction of the bridge by the year end.
Bangladesh recently signed a $2.76 billion loan deal with China’s EXIM Bank to implement the rail line project on the bridge.