'Mirpur-Airport travel in 15 minutes'
The communications minister on Friday said the flyover from Mirpur to Airport Road via Dhaka Cantonment and the overpass on Banani rail-crossing will be opened by March, 2013.
bdnews24.com News Service
bdnews24.com
Published :
06 Jan 2012, 03:45 PM
Updated :
09 Aug 2022, 03:16 PM
Dhaka, Jan 06 (bdnews24.com) – The communications minister on Friday said the flyover from Mirpur to Airport Road via Dhaka Cantonment and the overpass on Banani rail-crossing will be opened by March, 2013.
"Once the project is complete, commuting from Mirpur to Airport Road will take only 15 minutes and traffic gridlocks in the city be eased," Obaidul Quader told reporters after seeing the progress of the project.
Mentioning that different ministries and divisions are working to ease the traffic gridlocks, he said: "Most of the city roads connect the northern parts to the southern parts. This flyover will connect the eastern and western parts."
He expects that on completion of the Uttara-Jatrabari expressway, Kuril flyover and Gulistan-Jatrabari flyover, city traffic gridlocks will be eased to a great extent.
The minister visited Zia Colony intersection adjacent to the airport, Mirpur and Radisson Hotel area to see the progress of the Mirpur-Airport flyover project.
Earlier, project officials informed the minister of the progress at the Special Works Organisation office of the army.
They said works of all the 419 piles, 41 of the 52 pile caps, 17 of the 50 piers and three of the 216 girders of the flyover and all the 405 piles, 41 of the 50 pile caps, 25 of the 48 piers and 12 of the 241 girders have been completed.