Published : 16 Jun 2015, 11:11 PM
Updated : 23 Apr 2022, 12:49 PM
The meeting has been scheduled for June 18 in New Delhi to remove hurdles impeding the project aimed at linking Tripura capital Agartala with Bangladesh’s Akhaurha, a Tripura minister said.
Indian Prime Minister Narendra Modi, during his recent visit to Dhaka earlier this month, discussed the project with his Bangladesh counterpart Sheikh Hasina.
Tripura Transport Minister Manik Dey told reporters the meeting had been called by NITI (National Institution for Transforming India) Aayog, “to resolve the deadlock”.
Officials of the Tripura government, railways, the Ministry for Development of North Eastern Region and external affairs ministry will join the talks, to be presided over by the NITI Aayog chief executive officer or special secretary.
India and Bangladesh officials have so far had three rounds of meetings, and the joint survey and alignment work of the railway has been complete but land acquisition remains stalled in the absence of allotment of funds.
Around Rs 3.02 billion is needed to acquire around 98 acres of land in Tripura for laying new tracks.
The Rs 5.75-billion railway project was finalised in January 2010, when Bangladesh prime minister met her Indian counterpart at that time, Manmohan Singh, during her visit to New Delhi.
Recently, the state government again approached the railway ministry for funds since no money was allocated in the 2015-6 railway budget.
The initial cost of the 15-km railway track linking Agartala with Akhaurha was estimated at Rs 2.71 billion.
In addition, Rs 3.02 billion is needed to acquire around 98 acres of land in India for laying the tracks.
The Indian Railway Construction Company (IRCON) is expected to lay the tracks on both sides of the border with five kilometres in the Indian and rest in Bangladesh.