Published : 14 Jun 2015, 11:11 PM
Updated : 23 Apr 2022, 12:49 PM
Metro Rail Project Director Md Mofazzel Hossain told bdnews24.com the tender evaluation committee had almost finished scrutiny.
“Based on that, selection of the firms qualifying for the final bidding will be completed this month,” he said.
Hossain said financial proposals would be sought from those who would qualify technically.
“The final tenders will be invited on the completion of this process,” he said.
Pre-qualification bids were invited on Jan 30 for supply of the engine coaches. Thirty firms bought the tender documents but only eight submitted papers before the April deadline.
The contenders are China’s Norinco Group and Beijing Subway Company, Italy’s Ansaldo STS, France’s Alstom, India’s Bombardier, and Japan’s Consortium of Hitachi and Mitsui, Kawasaki-Mitsubishi Consortium and Nippon Psych-SC JV.
Metrorail Project Chief Engineer Sukumar Chandra Kundo told bdnews24.com that the contenders were globally renowned metrorail engine coach suppliers.
Kundo, also a member of the tender evaluation committee, said they were examining their work experience.
“We will be able to finalise the firms that qualify this month,” he said.
Every six metro rail engine coaches, known as electrical multiple units (EMU), will have two engines, one each on either end.
According to project documents, the construction of the metro will be completed in 2019.
Once ready, 24 pairs of trains will run to and from Uttara and Motijheel via Mirpur and Farmgate. They will carry 60,000 passengers in an hour touching every station once in every four minutes.
According to project officials, the trains will take less than 40 minutes to reach Motijheel from Uttara.
There will be 16 stations – Uttara North, Central and South, Pallabi, Mirpur-11, Mirpur-10, Kaziparha, Taltala, Agargaon, Bijoy Sarani, Farmgate, Sonargaon, National Museum, Doyel Chattar, Bangabandhu National Stadium, and Bangladesh Bank.
The project will cost Tk 220 billion, of which JICA will provide Tk 165.05 billion and the government will arrange the rest.
Tenders will be invited in six phases for different stages of the work with the last one being done in 2017.
Line alignment and designs of the 16 stations have already been finalised.
The Cabinet approved in principle the draft of the metro rail law on Apr 28.
Earlier, in 2012, the Executive Committee of the National Economic Council had given the go-ahead to the project.