Three units of Ashuganj station resume electricity production

Three malfunctioning units of the Ahsuganj Power Station in Brahmanbarhia have been restored after six hours.

bdnews24.com

Brahmanbarhia Correspondent

bdnews24.com

Published : 20 May 2015, 09:35 PM

Updated : 23 Apr 2022, 12:43 PM

The units resumed operation around 2pm after shutting down around 8am on Wednesday, said power station officials.
 
The units failed due to a mechanical malfunction, resulting in the station’s supply to the National Grid dropping by 264MW.
 
Power station Engineer Md Yakub told bdnews24.com that a 132-KV line had tripped at the switch yard substation.
 
“As a result, Unit-2 of 64MW capacity, Unit-3 of 150MW capacity and the 50MW gas engine unit shut down at the same time.”
 
The in-house engineers repaired the damage and the units resumed generation around 2pm, he said.