Petrobangla to take Madhyapara hardrock project sans manpower, preparation
Petrobangla is going to take up the Madhyapara hardrock project in May from the contractor firm NamNam without having any skilled manpower or preparation to run it.
bdnews24.com News Service
bdnews24.com
Published :
21 Apr 2006, 06:00 PM
Updated :
17 Aug 2022, 06:05 PM
Dhaka, Apr 22 (BDNEWS) - Petrobangla is going to take up the Madhyapara hardrock project in May from the contractor firm NamNam without having any skilled manpower or preparation to run it.
An official at the Petrobanlga told BDNEWS that there is no scope to run the mine without appointing a managing contractor like the Barapukuria. But there was no progress since the initiative was taken a year ago, he said.
The development work for the mine, which can provide 1.65 million tonnes of stones a year, is now at the fag end.
An official of the project said they would have to take the responsibility by June, if not in May. "But there will be no option rather than closing down the mine after its takeover in the present condition," he said.
Hard rock was discovered in the country in 1974 in Fulbari in the northern belt of the country, but it had to wait for a long time till 1994 to see its development.
The government had signed an agreement with North Korean company NamNam projecting the total expenditure for the project at US$ 152 million. The development work for the mine started a year later.
According to the agreement, the development work for the mine was scheduled to have been ended by 2001.
However, NamNam will have to pay a compensation at the rate of 16% for the delay, which will reduce the project cost by 16%. The life expectancy of the mine has been project at 50 years.
According to the agreement, the contractor firm was also responsible for creating human resources pool and skilled manpower for the mine and they trained up 12 workers from Korea, of whom six had already abandoned the project.
Despite that, it was agreed to train up 300 local people more. They first trained 100 people and 94 of them got certificates to run the mine. Training for 200 personnel more was not done in a proper way.
It was also agreed in the agreement that the trained personnel would be recruited for the project, but the reality was different as those trained people are now being lost. Now Petrobangla has no personnel to run the mine.
The only way to continue the work in the mine is to make another agreement with NamNam and run it with their manpower.
Considering the matter, Petrobangla has proposed NamNam to go for an agreement with 65 skilled manpower. But the proposal did not see any progress over last one year.
Concerned sources said, NamNam might go for proposing a higher rate under such circumstances for the proposal.
When his attention was drawn, Energy Adviser Mahmudur Rahman told BDNEWS that since there is no skilled manpower, the service for the mine will have to be provided by the contractors. "I don't think that it will be a major problem once we take the mine because, they did not complete the mine as yet."
BDNEWS/1825 hrs.