Niko defers relief well drilling at Tengratila
The Niko Resources has deferred the drilling of a relief well at Chhatak gas field, known as Tengratila.
bdnews24.com News Service
bdnews24.com
Published :
16 Jul 2005, 06:00 PM
Updated :
18 Aug 2022, 11:43 AM
Dhaka, July 17 (BDNEWS) – The Niko Resources has deferred the drilling of a relief well at Chhatak gas field, known as Tengratila.
The Canadian company in a meeting with its joint venture partner, Bangladesh Petroleum Exploration and Production Company Limited (BAPEX), Sunday expressed interest to drill a data acquisition well (DAW) before the relief well.
Presenting the new proposal, Niko officials said it is a preliminary offer and they will place the detail of the DAW at the end of this week.
Neither Niko nor the BAPEX did say anything formally about the new plan.
However, Niko officials said they want to drill the DAW as they do not want to take any risk.
"After acquiring the data, we will go for drilling of the relief well," said a Niko official.
He informed that the mission of the DAW will be completed by mid August. Then, drilling of the relief well will start by the end of the same month, he added.
A senior BAPEX official said: We don't have any experience in drilling a relief well. On the other hand, data acquisition well is a new thing for us. So, we can't comment on the matter until we get the full work programme from Niko.
The official, however, said that the proposal made by Niko in Sunday's meeting was preliminary part of third work programme of the Canadian company.
The work programme submitted by the Niko early this month was incomplete, the official said adding it was on only casing.
"As the Niko proposed a three-layer casing, the BAPEX asked to submit a full fledged proposal with four-layer casing," said the BAPEX official.
On that basis, he informed that Niko's consultant GSM of USA submitted the second work programme. "Before we discussed about the second proposal, the Niko came up with the third work programme," he told BDNEWS.
Tengratila experienced a blowout when the Niko under a joint venture with the state-run BAPEX had been drilling a well on January 7 this year.
The gas field witnessed the second accident on June 24 when the company was drilling a relief well to extinguish the fire originated by the first explosion.
Now it will have to drill another relief well.
BDNEWS/2111 hrs