Incomplete flyover would deprive people of Khilgaon and million others: Saber
Opposition leader Sheikh Hasina's political secretary Saber Hossain Chowdhury Wednesday said they are happy that the Khilgaon flyover is finally opened for traffic, but incomplete portion will deprive millions of people from getting its full benefit.
bdnews24.com News Service
bdnews24.com
Published :
22 Mar 2005, 06:00 PM
Updated :
17 Aug 2022, 08:22 PM
Dhaka, March 23 (BDNEWS) – Opposition leader Sheikh Hasina's political secretary Saber Hossain Chowdhury Wednesday said they are happy that the Khilgaon flyover is finally opened for traffic, but incomplete portion will deprive millions of people from getting its full benefit.
"If people vote Awami League back to power in future, we will complete the incomplete loop which will ease the traffic movement on the flyover, and facilitate the people of Khilgaon and other wide areas," he said.
Addressing a press briefing at his residence on the eve of inauguration of the flyover, the former lawmaker of Dhaka-6 constituency (now Motijheel-Sabujbag-Khilgaon) said the design of the flyover was changed for several times, an important loop was deducted and the width was narrowed down from 15 metres to 14 metres raising risk of traffic movement.
"Cutting off one loop from the flyover will deprive around 8 lakh people of the Khilgaon and other area like Rampura, Chowdhurypara, Meradia and Tilpapara to communicate quickly with Motijheel. Thus the main objective of the flyover will not be fulfilled," he said adding, "It's a big flaw in the design."
Saber said the main design of the flyover was made locally in such a way that it would have not need any traffic signal on the flyover easing traffic movement quickly. "Now, the curve was also risky as this was also changed," he said.
The Awami League organising secretary said the flyover took around 20 months more than the scheduled time costing millions of taka from the public exchequer and also caused huge public sufferings over the last three years.
The dilly-dally in project implementation was caused by many things, including lack of political willingness, toll collection by terrorists and repeated changes in design, he said.
"We are happy that it is now completed. We could be much happier if it was completed according to the original design," Saber opined.
BDNEWS/1445 hrs