Published : 13 Aug 2013, 08:44 PM
Updated : 09 Aug 2022, 11:00 AM
The city has been without electricity since Saturday night after a gas-fired 34.5MW rental power plant closed down following some technical glitches.
A PDB Executive Engineer was suspended over the incident.
Residents took out a protest procession from the city around Tuesday noon demanding restoration of power.
Witnesses said they encircled the PDB office and eventually attacked it in “utter frustration.”
Police soon intervened and took control of the situation, they said.
The West Zone Power Distribution Company, in charge of power supply there, could not say when the plant would be operational.
It said works were underway to replace a submarine cable of the gridline on the Tetulia River bed.
WZPDC Managing Director Abul Kalam Aazad told bdnews24.com Bhola would be connected with the national grid once the work is completed.
“The work will be completed within 12 hours,” he hoped.
Bhola power plant’s Manager Hafizur Rahman said Indian experts will reach on Wednesday. “The works on the plant would start after their arrival,” he said.