Published : 04 Nov 2024, 06:00 AM
Updated : 21 Aug 2026, 12:03 PM
Indian conglomerate Adani Power said it did not warn Bangladesh that it will switch off power supply to the country if there is no resolution on the payment of nearly $850 million in outstanding dues by Nov 7.
The Adani Group’s subsidiary also claimed that it is fully cooperating with the Power Development Board, or PDB, to resolve the issues tied to the dues.
Adani Power is supplying electricity to the PDB under a 25-year contract. The power has been supplied to Bangladesh since March last year from Adani's 1600 MW coal-fired power plant in Godda in the Indian state of Jharkhand.
The firm charges around Tk 12 per unit of electricity from Bangladesh. This price is 27% higher than that of other private producers in India and 63% higher than that of Indian state-owned enterprises.
Questions were raised over the issue during the previous government, but it remains unresolved. It is also "difficult" for the government to cancel the contract overnight as Bangladesh is getting about one-tenth of the power from Adani's power plant.
Meanwhile, a large amount of Adani's bills have been outstanding since the time of the previous government due to the dollar crisis. According to Indian media reports, the amount has already reached $850 million. Adani's representatives frequently visit Bangladesh to collect the dues.
Around 1400 to 1500 megawatts, or MW, of electricity was coming to Bangladesh every day from the two units of the Godda power plant. Adani shut down the power generation of a unit on Thursday due to non-payment of dues.
The company had previously set a deadline of Oct 31 for the PDB to clear the dues and opened a $170 million letter of credit, or LC, to secure payments, according to a report by the Times of India.
The PDB attempted to issue an LC through Krishi Bank, but this did not comply with the terms of the power purchase agreement, TOI reports.
The ongoing shortage of US dollars was cited as a significant reason behind the issue. In response, Adani's Godda plant slashed its supply starting Oct 31, exacerbating power shortages in Bangladesh.
According to a report published on the website of Power Grid Bangladesh, or PGB, the Indian company supplied 724 MW of electricity on Friday.
Meanwhile on Sunday, the TOI reported that Adani Power will stop supplying electricity to Bangladesh from Nov 7 if the arrears are not settled.
In reaction to the news, Power, Energy and Mineral Resources Advisor Fouzul Kabir Khan told bdnews24.com: "We paid them [Adani Power] about $98 million in October which is almost double compared to September.
“Besides, an LC of $170 million has been made via Krishi Bank for them. Such behaviour after that is very strange, stunning and sad."
Responding to another question, he said: "If Adani really shuts down the supply of electricity, we are ready to deal with it. We are taking steps to prevent customers’s suffering in that case,” he said.
'FRUSTRATING AND SHOCKING’
Shafiqul Alam, the chief advisor’s press secretary,
also expressed his disappointment over the media reports about the Nov 7 deadline set by Adani for the payment of outstanding dues.
At a media briefing at the Foreign Service Academy in Dhaka, he said: "The entire letter of Adani has not yet reached the Ministry of Power, Energy and Mineral Resources. If that's true, we're dismayed and shocked."
The press secretary said, “It is true that India's Adani Group’s subsidiary has outstanding dues for power import. We have accelerated the payment. The previous autocrat is mainly responsible for the backlog. They have left a huge backlog, due to which the amount has reached this level.
“We have taken steps to expedite the payment of our dues. The country's reserve has started to increase, international payments can be made without spending it. The remaining payment is $700 million. And we can settle it very quickly."
"We will not be held hostage by anyone or any individual power producer. No matter how powerful they are," Shafiqul said.