Country to wait till middle of April to get benefit of submarine cable
The country would have to wait till middle of April to get benefit of the submarine cable project at the user's end although the government plans to inaugurate it within the next month, project sources said Wednesday.
bdnews24.com News Service
bdnews24.com
Published :
21 Feb 2006, 06:00 PM
Updated :
17 Aug 2022, 05:51 PM
Dhaka, Feb 22 (BDNEWS) – The country would have to wait till middle of April to get benefit of the submarine cable project at the user's end although the government plans to inaugurate it within the next month, project sources said Wednesday.
Sources of Hesfibel and Harris Corporation, the contractors of the cable-installation project, said out of 156 km optic cable, installation of 105 km pipeline has been completed. The remaining pipeline installation and commissioning of microwave link between Cox's Bazar and Chittagong will be completed by March.
As it will to take at least two weeks more to complete the technical test of the link, the inauguration of the country's submarine cable project would not be possible before April 15.
However, T&T officials are hopeful of completing the remaining works by the middle of March and inaugurate the cable network by the next month.
"The remaining pipeline installation work would be over by next week and after testing, we are going to inaugurate it within this month," said Monwar Hossain, Director of Submarine Cable project.
Earlier, the project was scheduled to be inaugurated within February.
Officials of the foreign contractors said, if the project is inaugurated before completion of the entire work, it would hamper the total project. The technical work with proper cable-installation should be given a minimum time.
Even if the project is inaugurated, benefit would not go to the user's end just after the inauguration.
The countrymen could only get the full benefits of fast internet and international telephone services with ensuring connectivity between the super highway and the internet service providers (ISPs).
But government's efforts in this regard are absent, Internet service providers alleged
A non-discriminatory policy and regulation for using the bandwidth of the submarine cable ensuring cost-effective access to essential facilities is yet to be framed, they added.
However, the T&T board has already started using the submarine cable on experimental basis, BTTB sources said.
The project would increase the number of international circuits facilitating voice and data transfer easier and speedy. Besides, other services like broadband data transfer, call centre services, software exports, e-government, e-commerce, Tele- medicine etc would be cheaper and easier, he added.
Akhtaruzzaman Manju, President of the Internet Service Providers Association, Bangladesh (ISPAB), said that government should provide sufficient bandwidth at a low cost to make the internet affordable for the users.
BDNEWS/1817 hrs