Published : 17 Jun 2014, 07:56 PM
Updated : 08 Aug 2022, 06:52 PM
While four of them are new, two others are revised projects.
The approvals came at a meeting chaired by Prime Minister Sheikh Hasina on Tuesday.
Of the total cost, the government will bear over Tk 9.97 billion, Planning Minister AHM Mustafa Kamal told reporters after the meeting.
The rest of the money, a little over Tk 10.1 billion, will come as project assistance, he said.
The total cost of the first project, Flood and Riverbank Erosion Risk Management Investment Programme (Tranche-I), is Tk 8.28 billion.
Of this, the government will bear Tk 1.86 billion, while Tk 6.42 billion will come as project assistance. Bangladesh Water Development Board (BWDB) will implement the project by December, 2018.
The Irrigation Management Improvement (IMIP) for Muhuri Irrigation Project will cost Tk 4.57 bn. BWDB will implement the project by June, 2019.
The ECNEC gave nod to Comprehensive Water Management for West Gopalganj Project with a total cost of Tk 1.22 bn. BWDB will implement the project by June, 2016.
Construction of the Postal Department headquarters at Dhaka’s Sher-e-Bangla Nagar, involving an outlay of Tk 547 million, was also approved. The department is expected to complete the project by June, 2017.
The ECNEC also approved two revised projects ‘Construction of Cox's Bazar-Teknaf Marine Drive’ and ‘Construction of 217.15-metre-long PC Girder Bridge on Sangu River on Chimbuk-Ruma Road’ in Bandarban aiming at boosting tourism.
Ministers, state ministers, members of Planning Commission and secretaries concerned to the projects were also present in the meeting.