Rolling outage is staging a comeback with the mercury on the rise.
Bangladesh Power Development Board says ‘load-shedding’ has increased as gas crisis cut power generation by over 1,100 megawatts.
The PDB in its electricity production and distribution forecast for Tuesday said 176 MW of outage might happen against the highest demand of 6300 MW.
According to PDB data, the nation suffered 101 MW of outage on Monday.
PDB Member (Production) Tamal Chakrabarty told bdnews24.com: “For several days there was no load-shedding. Now the demand has increased. But it (load-shedding) is less than what was in previous years.”
He said inadequate gas supply was mainly responsible for the supply crunch.
According to PDB statistics, gas crisis cut production by 1,102 MW and technical glitch by 799 MW on Tuesday.
Petrobangla said 916 million cubic feet (mmcf) of gas went to the power plants on Tuesday against their demand for 1,339 mmcf though Petrobangla earlier said daily demand-supply gap will be around 450 mmcf.
The PDB now has to depend more on oil-based generation by private producers.
According to statistics, 127.13 million kilowatt hours of electricity were produced on Monday. Of that 87.7 million kWh were generated from gas, 33.85 million kWh from oil, 3.87 million kWh from coal and 1.71 million kWh from water.