Dhaka, July 13 (bdnews24.com) — The government has gave the green signal for setting up a 150 MW power plant in Sirajganj.
The Executive Committee of the National Economic Council (ECNEC) on Tuesday approved the 'Sirajganj 150 MW Gas Turbine Peaking Power Plant (Amended) Project' worth Tk 9.62 billion.
Of the total cost, Tk 5.82 billion would come from the state coffer while the remainder is expected from development partners.
The project's initial cost was estimated at Tk 6.87 billion and was scheduled to be completed by June 2009, when it was first approved in 2007.
Later the completion deadline was extended twice till June 2012, without any increase in the cost.
According to an agreement between the Asian Development Bank and the government, signed in June 2007, the ADB was supposed to fund Tk 4.33 billion to implement the project.
The, project, however, failed to take off due mainly to bureaucratic red tape and "corruption issues", said an official of the planning commission, asking not to be named.
The ADB on June 14 approved an assistance of $25.22 million and € 21.42 million for the project, added the official.
The Power Development Board (PDB) proposed to revise the budget upward because of the rise in cost of machineries in international market and new salary structure for the officials and employees, according to documents obtained by bdnews24.com.
The Northwest Power Generation Company Limited (NWPGCL) under the PDB is the implementing agency for the project, which is expected to finish by June, 2012.
Tuesday's ECNEC meeting altogether approved five projects worth Tk 14.19 billion including a Tk 2.32 billion project of the health ministry to set up the National Institute of Neuroscience.