Gas from Haripur-7 expected in couple of months
Gas production from Haripur-7, which was earlier an oil well, is expected in a couple of months, officials concerned said.
bdnews24.com News Service
bdnews24.com
Published :
03 Mar 2005, 06:00 PM
Updated :
17 Aug 2022, 08:16 PM
Sylhet, March 4 (BDNEWS) – Gas production from Haripur-7, which was earlier an oil well, is expected in a couple of months, officials concerned said.
They said turning the oil well into gas one has successfully been completed. "Drill stream test (DST) and other required tests were found to be successful," said an official.
"We are expecting 15 MMCFD (million cubic feet per day) of gas from the well by April," he said.
Preparations are on to set up a three-kilometre pipeline from the well to nearby gas processing plant for supplying to the national grid.
The much-talked-about well-7 of Haripur gas field under Sylhet Gas Field Company Limited (SGFL), a subsidiary of state-run Petrobangla, had been sealed off for long 10 years.
Officials said the work on the well for producing gas began on December 15, 2004.
The SGFL in cooperation with Bangladesh Petroleum Exploration and Production Company Limited (BAPEX), another company of Petrobangla, has been implementing the project for developing the well.
The project cost is Tk 130 million, including Tk 70 million in foreign exchange.
The prospective well was first drilled in 1986 with assistance from Asian Development Bank (ADB).
It was drilled targeting gas, but more than one gas layers and a well zone were noticed before the drilling reached the targeted depth.
Officials said as the discovery of oil zones was considered as a significant event for oil exploration, oil production started from the well.
"The well produced 560,000 barrels crude oil from December, 1987 to July, 1994," an official said adding later oil production was suspended due to pressure problem.
Since then the well remained sealed off.
A seismic survey in early 70s found that Haripur structure has a gas reserve of 683.85 billion cubic feet (BCF), with 444.6 BCF explorable. Presently, the structure has 275 BCF explorable gas.
corr/zn/ni/1250 hrs