November 23, 2026

Funding uncertain for Dhaka’s Shahjalal International Airport expansion project

Uncertainty looms over the construction of a third terminal at the Shahjalal International Airport in Dhaka due to lack of fund for the project.

Zafar Ahmed

and Ashik Hossain

bdnews24.com

Published : 09 Dec 2015, 12:24 PM

Updated : 23 Apr 2022, 01:21 PM

Lenders and aid agencies, which had previously shown interest to invest in the project, now appeared to be getting cold feet.

Civil Aviation Minister Rashed Khan Menon said talks are on with some Chinese companies to implement the project. But, he too could not spell out anything about funding.

Meanwhile, the Civil Aviation Authority of Bangladesh (CAAB) said they approved the ‘master plan’ and forwarded it to the planning ministry. The ministry will decide about the finance, according to CAAB.

In May this year, the detailed proposal for expanding the Dhaka airport, which includes building a third terminal, another runway and other infrastructural developments, was forwarded to the Prime Minister’s Office.

The proposal says the airport now has the capacity to handle around eight million passengers annually. But in the first five months of 2015 it handled 6.7 million passengers.

With a 9.5% yearly increase in passenger volume, the limit is expected to be crossed in 2018.

Prime Minister Sheikh Hasina has told officials to implement the project on a priority basis. But the process has been stalled as neither JICA, the South Korean government nor the Kuwait Fund is agreeing to finance the project.

A civil aviation ministry’s Aug 5 report says the Japanese government or Japan International Cooperation Agency (JICA) did not respond to the Economic Relations Division’s (ERD) letter on funding this project.

Meanwhile, an ERD report says that the civil aviation ministry has been asked to initiate measures to arrange funds from the Chinese government.

The project is also not included in the eight projects to be funded by South Korea under its Economic Development Cooperation Fund (EDCF) Framework Arrangement.

And its estimated cost exceeds Kuwait Fund’s ceiling for funding a project, says the report by the ministry.

Civil Aviation Minister Rashed Khan Menon told bdnews24.com that they had ‘short-listed’ some Chinese organisations for the job. “We wanted to start the project in March or April, but it appears unlikely to me. It will be possible to start it by June or July.”

“If everything goes according to plan, then the project can be tabled before the ECNEC within a month and half,” he added.

The minister though appeared optimistic, it’s clear from the civil aviation authority’s statement that the issue of funding is yet to be settled.
 
“The project has been approved and the civil aviation ministry has forwarded it to the planning ministry, which will initiate measures for funding,” said CAAB Chairman M Sanaul Haque.
 
On May 20, the ‘China Airport Construction Group Corporation’ sent several proposals, including one for expansion of the Dhaka airport, directly to Prime Minister Sheikh Hasina’s office.
 
Documents obtained by bdnews24.com show that as per the company’s estimate it will require $1.3 billion for expansion of the airport, which includes construction of two terminals—international and domestic-- and a cargo village.
 
But the government is yet to respond to the proposals.

Related Stories