Published : 24 Oct 2015, 02:21 AM
Updated : 23 Apr 2022, 01:13 PM
Without naming the firm, the minister said on Friday that he had ‘called on’ the Spanish ambassador several days ago and gave him and the company, ‘which has worked at Bibiyana and Siddhirganj’, a deadline to return the engineers.
“They will have to return within Nov 5 and I will penalise them,” Hamid said, after laying foundation stone of the zonal office of Naryanganj Palli Bidyut Samity-2.
“I don’t think there is anything in Bangladesh that could lead the foreigners to feel unsafe,” Hamid said.
The government signed an agreement with two foreign construction companies for Siddhirganj 335-megawatt Combined Cycle Power Plant (CCPP) project in Narayanganj district.
Corsán got the job in October 2011 to set up the 340 megawatt combined cycle power plant.
It was supposed to finish the job within 2014 in line with the contract but could not meet the deadline.
The work stopped when the firm withdrew its 43 engineers citing security concerns on Oct 7 following the murders of two foreigners.