Published : 01 Apr 2014, 07:21 PM
Updated : 19 Oct 2022, 07:26 PM
A fault in the marine cable led to the shutdown of the gas-based plant, owned by Sinha Group’s Venture Energy Resources Ltd, in August last year.
The 34.5 MW plant could never produce power without interruption since its commissioning in June, 2009 due to various mechanical problems. The Ministry of Power has also done nothing to address the issue.
Bhola district requires 30MW of electricity per day during summer. With the closure of the rental plant, it now entirely relies on the 8 to 12 MW of power it gets through the marine cable from Patuakhali and Barisal, which are connected to the national grid.
“The plant was set up Alstom, a French company” said Hamudur Rahman Khan, the plant’s former director (engineering). “New parts were bought from China, and not France, when it stopped working.”
“So it’s taking time to be fixed.”
It will start functioning within one week, said Hafizur Rahman, Venture Energy Resources Ltd’s manager in Bhola.
“The plant’s authorities are very incompetent and that is why they are failing to keep promises to keep it operational,” said Md Ali, executive engineer for West Zone Power Distribution Company.