Overloading wastes Tk 400 crore each year
About Tk 400 crore goes down the drain every year because of overloaded trucks or lorries. Experts say the amount could be saved if weight measurement rules could be enforced. They say overloading also causes more pollution. Officials of the Roads and Highways Department say a highway, which is supposed to sustain 10 years, becomes unusable within four to five years because trucks or lorries usually carry goods beyond their permissible weight limits.
bdnews24.com News Service
bdnews24.com
Published :
22 Feb 2007, 11:33 AM
Updated :
17 Aug 2022, 02:29 PM
Kamran Reza Chowdhury
bdnews24.com Senior Correspondent
Dhaka, Feb 22 (bdnews24.com) - About Tk 400 crore goes down the drain every year because of overloaded trucks or lorries.
Experts say the amount could be saved if weight measurement rules could be enforced. They say overloading also causes more pollution.
Officials of the Roads and Highways Department say a highway, which is supposed to sustain 10 years, becomes unusable within four to five years because trucks or lorries usually carry goods beyond their permissible weight limits.
Most of the amount allocated each year for road repairing is wasted due to overloading.
"Out of the total annual allocation of Tk 500 crore for repairs, the roads department spends more than Tk 400 crore to just repair the damages caused by overloading," Rafiqul Islam, a superintendent engineer of the RHD and head of its Highway Design Module wing, told bdnews24.com Monday.
According to a 16 November 2003 order of the communications ministry, a standard heavy truck cannot carry more than 10 tonnes of goods. But an October, 2006-study of the roads department showed that on an average, a standard heavy truck usually carried up to 20 tonnes of goods. Such practice is a complete violation of the official rules.
As per the Motor Vehicle Ordinance, 1983, the law- breakers are supposed to be fined Taka one thousand for the first time and handed down up to six months of prison term along with Taka one thousand for a repeat of the violation.
"I have never heard that anyone had been imprisoned for overloading," Humayun Rashid Khalifa, director (engineering) of the Bangladesh Road Transport Authority, told bdnews24.com Thursday.
At present four weighing machines are in operation in key places of the country: one in Auskandi on Dhaka-Sylhet Highway, one in Shitakunda on Dhaka-Chittagong Highway, one in Bathuli on Dhaka-Aricha Highway and the final one is in Keraniganj on Dhaka-Mawa Highway.
Weighing machines on both sides of the Jamuna bridge and another at Mazar Road in Dhaka do not work.
Khalifa told bdnews24.com that if the trucks carried permissible weights, the environment pollution could be lower.
When a truck is overloaded, it moves slowly resulting in inefficient burning of fuels. The inefficient burning of fuels lead to emission of more air pollutants like carbon monoxide and dioxide, also responsible for climate change.
The roads department officials say the department spends up to Tk 80 lakh for repairing one kilometre road (32 feet wide) with bituminous concrete.
According to the latest roads department statistics, the country has 3,520 kilometres of national highways, 4,280 kilometres of regional highways and 13,753 kilometres of the Zilla roads.
Rafiqul Islam said a truck carrying 20 tonnes of load causes 30 times more damage to the roads than does a truck carrying 12 tonnes of weight.
bdnews24.com/krc/jr/ah/1726 hours