The third terminal is being constructed at the cost of Tk 214 billion at the south end of Shahjalal International Airport’s main terminal in Dhaka. The Japan International Cooperation Agency is financing a part of the project. The rest will be provided by the government.
Almost 77.7 percent construction work of the third terminal at Shahjalal International Airport is completed, according to the Civil Aviation Authority of Bangladesh.
The three-storey modern terminal building has a floor space of 230,000 square metres.
The newly constructed terminal building will have 64 departure and 64 arrival immigration desks, 27 baggage scanning machines, 40 scanning machines, 12 boarding bridges, 16 carousels and 11 body scanners.
The grand terminal building of Shahjalal International Airport in Dhaka is almost complete. Currently, the interior decoration and installation of various equipment are in progress.
The construction of underground tunnels and flyovers along with the third terminal building is also under way.
Metrorail and Dhaka Elevated Expressway will be connected with the new terminal.
If everything goes well, parts of the terminal, equipped with modern passenger facilities, will open on a trial basis in the first week of October, according to the Civil Aviation Authority of Bangladesh.