Four-lane road becomes rundown within a month of construction in Rangpur City

An eight-kilometre stretch of a four-lane road in Rangpur City, constructed at a cost of Tk 420 million, has become impassable within a month of its construction.

Rangpur Correspondent

Shahajada Mia Azad,

bdnews24.com

Published : 15 Aug 2015, 10:31 PM

Updated : 23 Apr 2022, 01:00 PM

Engineers have blamed “irregularities and negligence” on the part of the contractor for it. But the contractor claimed he had constructed the road fulfilling conditions set in the tender.

Two engineers from Roads and Highways Department’s road research laboratory are in Rangpur to examine the condition of the road from the city’s ‘medical intersection’ to ‘modern intersection’.

Explaining the situation, Executive Engineer Salma Akter said the road’s base was not properly constructed during the upgrading and it subsided after heavy vehicles ran on it.

Water accumulated in the low spots, wearing off the carpeting and forming ditches.

“There are both irregularities and negligence in constructing the road,” she told bdnews24.com. “We are looking into it.”

Rangpur’s central truck terminal is located beside the road.

Shahidul Islam Manik, General Secretary of Rangpur’s Truck and Tank Lorry Workers’ Union, said their vehicles could not use the rundown road.

Rangpur RHD was tasked with upgrading a 16.24-km stretch of road in the city to four lanes with a Tk 1.26 billion budget.

The work started on Mar 20, 2011 and ended on June 30 this year.

Prime Minister Sheikh Hasina inaugurated the road through a teleconference from the Ganabhagban on July 14.

Rangpur RHD’s Executive Engineer Abdullah Al Mamun said the carpeting had worn off on a 330-metre stretch of the road in the first week of July.

Contractor firm ‘Ms Masuma Begum’ did the bituminous carpeting work for Tk 90 million.

Mamun said the contractor had been paid for its work.

“The contractor started repairing the road following our order since Thursday,” he said.

He skirted a direct reply about the RHD’s supervision quality saying he had joined work at Rangpur for about 10 months.

“Only the bituminous carpeting surface work was completed during this time,” he added.

Contractor Raju Ahmed said they fulfilled the requirement mentioned in the tender.

“It’s not our responsibility if the road wears off after completion,” he said. “But we’re repairing it on RHD’s order.”