Fault in distribution line: Many areas of capital out of electricity, Lead
A vast areas of the capital remained out of electricity supply hours after hours Monday.
bdnews24.com News Service
bdnews24.com
Published :
05 Mar 2006, 06:00 PM
Updated :
17 Aug 2022, 05:54 PM
Dhaka, Mar 6 (BDNEWS) – A vast areas of the capital remained out of electricity supply hours after hours Monday.
Officials said that power supply systems in areas under Dhanmondi, Karwanbazar and Ramna substations of Dhaka Electric Supply Authority collapsed at 5 am Monday.
The areas went out of electricity as the electricity supply was snapped following a fault in the second 132-kv Ulan-Dhanmondi line.
As a result, officials said, 80 MW power supply from Ulan to Dhanmondi remained suspended.
The supply through the first 132 kv Ulan-Dhanmondi remained suspended since the holy Eid-ul-Fitr on January 11, after a fault was developed in it.
Following the fault in the second line, they said power supply was off in Dhanmondi, Rayer Bazar, Mohammadpur, Rajabazar, Indira Road, Karwanbazar, Ramna and Naya Paltan for four hours from 5 in the morning.
Later, in some areas electricity was supplied, but it was only for a brief time.
In some areas, supply disruption took place for 20-25 times.
In addition to that the city witnessed severe low-voltage problem hampering trade and production.
A generator at Jahangir Tower, known as Ekushey Television Bhaban at the city's Karwanbazar, was caught by fire twice due to running hours after hours following the electricity supply problem.
"Officials and employees were evacuated from the building," said a witness account.
The BDNEWS office situated on the seventh floor of Jahangir Tower was out of electricity supply almost all the day disrupting its operation seriously.
SSC examinees in different parts of the capital had also to suffer a lot. Their exams begin on March 9.
DESA chairman Towhidul Islam said that the latest fault on the Ulan-Dhanmondi distribution line could not be repaired shortly.
He informed that the machinery and experts for repairing the first distribution line are expected to arrive in Dhaka on April 4.
Then it will take 3-4 weeks to repair the line.
"We are trying to bring machinery also for repairing the second line," the DESA chairman said.
According to the DESA officials, the demand in the areas under Dhanmondi, Karwanbazar and Ramna substations is 120 MW.
After developing fault in the first line, 80 MW electricity was being supplied through the second line while rest 40 MW from other alternative lines.
DESA chairman claimed that the shortage in the area will be 40 MW after ensuring supply from the alternative lines as now the both regular lines are out of order.
However, a source said that the shortage in the peak hours now will be 60 MW.
Officials are apprehending that the crisis situation will continue till first week of May.
BDNEWS/2045 hrs