November 20, 2026

HC declares immunity provision in quick rental law illegal

The Quick Enhancement of Electricity and Energy Supply (Special Provisions) Act was enacted by the Awami League government in 2010

 Senior Correspondent

bdnews24.com

Published : 14 Nov 2024, 07:35 PM

Updated : 21 Aug 2026, 12:04 PM

The High Court has ruled that the immunity provision under the Quick Enhancement of Electricity and Energy Supply (Special Provisions) Act 2010, which regulates quick rental power plants, is illegal.

The bench of Justice Farah Mahbub and Justice Debashish Roy Chowdhury issued the ruling on Thursday.

Previously, on Sept 2, the court had issued a rule questioning the legality of the immunity and procurement-related sections of the quick rental legislation.

When the Awami League government assumed power in 2009, it approved several rental and quick rental power plants to swiftly address a power crisis.

However, the government had to pay substantial subsidies to purchase electricity from these plants at high prices, which ultimately burdened taxpayers. The practice has drawn intense criticism.

To legalise the rental power plants, the 'Quick Enhancement of Electricity and Energy Supply (Special Provisions) Act' was enacted in 2010. Although it was initially intended to be in effect for just two years, the act's duration has been extended several times since.

Supreme Court lawyer Tayeb-Ul-Islam filed a writ petition challenging the legality of sections 6(2) and 9 of the statute. Lawyer Shahdeen Malik represented the petitioner.

Section 6(2) provides that any procurement, investment plan, or proposal must be approved by the energy minister and sent to the cabinet committee for its greenlight after negotiations with a single or limited number of organisations.

Section 9 states that no court shall have jurisdiction to challenge the legality of any action taken, measure adopted, or order issued under or deemed to be under the Act.