November 23, 2026

BGMEA must stop seeking more time for building demolition: Court

The Appellate Division has ordered garment exporters’ organisation BGMEA to sign an undertaking that it will not file further petitions seeking time to demolish its illegally constructed building.

Staff Correspondent

bdnews24.com

Published : 27 Mar 2018, 11:26 AM

Updated : 08 Apr 2022, 03:03 PM

On Tuesday, a four-member bench led by Chief Justice Syed Mahmud Hossain stated that it would consider BGMEA’s plea for one more year but first, it has to sign the undertaking.

Built illegally on endangered wetlands in Dhaka about two decades ago, the 19-storey BGMEA building was called ‘a cancer’ on the Hatirjheel Beautification Project by the High Court.

In 2011, the High Court found that the building had been constructed by violating the law meant to protect wetlands and ordered its demolition. The court said the building was hindering the water flow of Begunbari canal and hampering the Hatirjheel project.

A review petition on the decision was dismissed by the Appellate Division and the BGMEA was told to complete demolitions by Sept 12. An additional seven-month extension granted on Oct 8 last year ends on Apr 12.

The court told the BGMEA at the time extension hearing that more time would not be granted.

But the BGMEA filed another petition on Mar 5 seeking a full-year extension.

The top court heard the petition on Sunday and set Tuesday for the date of the decision.

The court however, refrained from declaring any decision as the BGMEA agreed to sign the undertaking.

BGMEA’s petition will be considered once it signs the undertaking, the court said.

Lawyers Kamrul Haque Siddique and Imtiaz Moinul Islam represented the BGMEA at the hearing, while the state was represented by Attorney General Mahbubey Alam.