Road Transport Advisor Fouzul Kabir Khan had travelled to Brahmanbaria to inspect traffic woes on a dilapidated stretch of the Dhaka-Sylhet Highway. Caught in the very gridlock he had set out to review, he eventually abandoned his car and continued the journey on a motorcycle.
Jahangir Alam, chief of Brahmanbaria's Khatihata Highway Police Station, said the advisor arrived at the Bishwa Road intersection on a motorcycle around 1:05pm on Wednesday, where he inspected the state of the road.
“About 40 minutes later, his car, which had been stuck in traffic, arrived at Bishwa Road. The advisor then left for Ashuganj in his car."
The 12km stretch between Ashuganj and Bishwa Road usually takes about 30 minutes to cross. However, for the last few months, disrepair has made the journey take several hours, leaving commuters facing extreme suffering.
Work is under way to upgrade the 51km road from Ashuganj River Port to Akhaura Land Port to four lanes. However, the project is progressing slowly.
As a result, traffic jams from the Ashuganj roundabout to the Sarail-Biswa Road intersection on Dhaka-Sylhet Highway have become a regular ordeal. Authorities began to fill the potholes on the road on Sunday ahead of the advisor's visit.
The move has led to three consecutive days of severe gridlock in the area as one side of the road was closed.
On Wednesday morning, the advisor reached Bhairab Railway Station in Kishoreganj on the "Mohanagar Provati" train. Later, on his way to Brahmanbaria by road, he stopped at Hotel Ujan Vati in Ashuganj.
The advisor then got stuck in severe traffic congestion in the Maitree Stanbha area of Ashuganj.
As vehicles remained rooted to the spot, the advisor decided to take a motorcycle ride to reach his destination.
The Roads and Highways Division and the district administration said the project worth Tk 57.91 billion is being implemented by Indian contractor firm “Efcons Infrastructure Limited.”
After the fall of Sheikh Hasina government, the project, funded by Indian loans and local funding, came to a halt. The officers of the Indian company stopped the work and went back home. They returned three months later and resumed the work.
Meanwhile, many of their materials were lost. After Aug 5, last year, the project progressed slowed down. As per the demand of the company, the government allotted Tk 1.63 billion more in funding.