Published : 25 Aug 2024, 01:50 AM
Updated : 21 Aug 2026, 11:48 AM
Authorities at the Karnaphuli Hydroelectric Power Station have decided to postpone the opening of the Kaptai dam spillway gates from night to the following morning.
The 16 spillway gates, originally set to open at 10pm on Saturday, will now be opened at 8am on Sunday.
ATM Abduzzahar, the manager of the power plant, said: “We initially planned to open the gates at night. However, due to lower water flow and to avoid potential night-time risks, we decided to
delay the opening.”
The gates will be opened by six inches each, as previously decided.
Sakhawat Kabir, assistant director of the power plant, said the water level in the lake was recorded at 108 feet mean sea level at 10pm, which was below their expectations.
Earlier, the decision was made to open the gates to release 9,000 CFS of water into the Karnafuli River.
This measure was taken as the water level in the Kaptai Lake approached its capacity and reached near-danger levels.
They also mentioned that if rainfall or water flow increases, the gates will be opened further.
The decision to open the gates was taken to manage flood risks both upstream and downstream, said Abduzzaher.
Currently, five units used for power generation are discharging an additional 32,000 CFS of
water, generating about 219 MW of electricity, he added.