Published : 28 Jul 2025, 08:53 PM
Updated : 21 Aug 2026, 01:34 PM
A torrent of 64mm of rain over three hours on Monday morning has caused waterlogging across the port city of Chattogram, with some roads submerged in water up to waist height and others knee-deep.
The water has entered stores in certain markets.
Commuters, Higher Secondary School examinees, and others faced difficulties navigating the flooding in the city.
The Patenga Meteorological Department says the rain is expected to last throughout Monday, and more rain is on the way on Tuesday and several days after that.
The rain caused waterlogging in Kapasgola, Katalganj, Chawkbazar, Panchlaish, the Prabartak intersection, GEC, Muradpur, AK Khan Gate, Agrabad Commercial Area, Tin Pole Matha, Riazuddin Bazar, Hemsen Lane, and Jubilee Road.
Mayor Shahadat Hossain inspected several areas of the city and nearby hills that were at risk after the heavy rain in the morning. The Chattogram City Corporation has started making public service announcements in those areas at risk in the hills.
The control room of the Meteorological Office's Ambagan Centre said that 64mm of rainfall was recorded in the three hours from 9am to noon on Monday.
The 24 hours to noon on Monday saw 102mm of rain.
"Moderate to heavy rain will continue throughout the day today. From tomorrow, it will rain for another two to three more days. However, the intensity of the rain may decrease slightly," Mahmudul Alam, a forecaster at the Patenga Meteorological Office, told bdnews24.com.
In the Katalganj area, the water is nearly up to waist height. Pedestrians are taking a risk by walking on the road divider. Aside from rickshaws, not many vehicles are on the roads.
The water is nearly knee deep in the middle of the road in the Tin Pole Mata area. It has also risen on the ground floor of the nearby Golam Rasul Market. Several shops in the nearby Riazuddin Bazar also saw waterlogging in the morning.
Samiul Haque, a resident of Kapasgola, said, "The water rises every month. Whenever there is heavy rain, our area is submerged. Despite all the efforts that are underway, the water still rises."
Mayor Shahadat, while inspecting the Kapasgola and Katalganj areas of the city, said: "We have been able to reduce waterlogging by 50 percent. It is a matter of time. The CDA is working on 36 out of 57 canals. Of these, the work on 22 canals has been completed. The work on 14 canals is still pending. Apart from this, work on another 20 remains pending. We also have to renovate them.
"The main canal in this area is the Hijra Canal. It extends from Kapasgola to Katalganj. Once the renovation of this canal and the work on the drain are completed, it will solve the problem in this area.”
Stating that work will be done to raise the roads in the area after the rainy season ends, Shahadat pointed to the examples of the Bahaddarhat, Muradpur, and Mirzapul areas, which also used to face waterlogging.
Since demolishing a market over the drain, the waterlogging has eased substantially, he said. Work on a box culvert is underway in Agrabad. He hopes that the waterlogging in the area will reduce sharply once it is completed.
Stating that waterlogging does not persist throughout the day in the city as it did before, Shahadat said: “Now, the water recedes one and a half to two hours after the rain stops.”
The Bangladesh Meteorological Department's forecast on Monday said that a well-marked low-pressure area located over Madhya Pradesh and the adjoining areas of India has moved west-northwestwards and weakened into a low-pressure system and merged with the axis of the monsoon.
The axis of the monsoon extends from Rajasthan, Uttar Pradesh, Madhya Pradesh, Bihar, West Bengal and the southern parts of Bangladesh to Assam. The monsoon is active over Bangladesh and is moderate in the north Bay of Bengal.
On Jul 9, several parts of the city were submerged in 70.6mm of rain over the course of three hours from 9am to noon, including the GEC intersection, Tin Poler Matha, Katalganj, Chawkbazar, Halishahar, Baklia, Agrabad, Goalpara and EPZ areas.
Jun 18 also saw 89mm of rain from 6am to 9am.
Work is underway on four projects, including the Chattogram Development Authority (CDA) mega project, to resolve the city's decades-old waterlogging problem. The total cost of these projects is estimated at nearly Tk 144 billion.
Of these funds, the project being implemented by the CDA to resolve waterlogging by repairing and renovating 36 canals costs Tk 86.26 billion. The timeframe for the project’s implementation will end in June next year.
The project is 84 percent complete. Of the 36 canals, work is complete on 25 canals. Of the remaining canals, the work on six others is more than 90 percent are complete, and that on five others is less than 90 percent complete.
The city's Katalganj, Panchlaish and Muradpur areas surround the Hijra Canal. The excavation and renovation work of the canal in the area has yet to be completed.
In addition, the Chattogram City Corporation has identified the clogging of the nearly three-kilometre-long box culvert with garbage as one of the main reasons for waterlogging in the Agrabad area. Now, the work of cleaning it is underway.