No structural design on deep seaport yet: Quayes
Despite China's commitment to provide assistance a year back for the deep seaport, the proposal on its structural design is not ready yet, says a senior official.
bdnews24.com News Service
bdnews24.com
Published :
25 Jun 2011, 09:49 AM
Updated :
10 Aug 2022, 05:00 PM
Dhaka, June 25 (bdnews24.com) — Though one year has elapsed since China's commitment to provide assistance, Bangladesh is yet to provide it with a proposal of structural design on the deep seaport, the foreign secretary has said.
"Since the official assurance form the Chinese vice-president during his visit last year, we've been working on a proposal with a structural design for the project. However, it has not been finalised yet," Mijarul Quayes told reporters on Saturday.
No country has made any commitment yet of any amount as Bangladesh has not provided any proposal on structure of the deep-sea port, he said.
"Any project has two kinds of homework -- agreeing in principle and finalising the ideas, and creating a detailed structural proposal on the project.
"We've completed the first. The second task is very complicated as it involves inter-ministerial matters, which we're doing," he added.
According to the shipping ministry, the government has taken steps to set up a deep-sea port at Sonadia Island of Moheshkhali in Chittagong.
There will be five international standard jetties at the port, which will be capable to handle 704.01 million tonnes of containers every year.
The total cost of establishing the port in three phases has been estimated at around Tk 600 billion, but the cost may go up in the future.
The first phase of the port is expected to be completed by 2020 with an estimated cost of Tk 130 billion.