SPECIALTk 1b ICDDR,B fund squandered?
The premier institution goes under the government scanner for alleged misuse of funds meant for expansion purposes.
bdnews24.com News Service
bdnews24.com
Published :
22 Jul 2011, 03:01 PM
Updated :
10 Aug 2022, 05:09 PM
Nurul Islam Hasib
bdnews24.com senior correspondent
Dhaka, July 22 (bdnews24.com) – The research organisation International Centre for Diarrhoeal Disease Research, Bangladesh (ICDDR,B) is under scanner for alleged misuse of government's funds allocated for expansion purposes.
A four-member committee has been appointed by the health ministry to look into the use of the ministry's Tk 1-billion fund, which was disbursed in three parts to complete vertical expansion of the Centre's three-storey Mohakhali building into eight-storey by 2009.
But the project started in March 2006 could not be completed and now has come to a halt.
bdnews24.com has obtained copy of a ministry notification, wherein questions have been raised on the way project was executed.
In view of certain complaints, the notification states, the ministry felt it imperative to look into the matter 'to ensure transparency and accountability'.
The document circulated to the officials concerned says that even though ICDDR,B could not complete the expansion of the initial projects, new projects were approved on the Centre's proposal.
Joint secretary (administration) SM Ashraful Islam has been made the convenor, while deputy chief (family welfare) Mohammad Helal Uddin is the member secretary of the committee formed on July 3.
Deputy secretary (admin-3) Mohammed Alfaz Hossain and executive engineer of the Health Engineering Department's Dhaka Division Mohammed Golam Haider Khan complete the committee as members.
However, even the committee that was supposed to complete the task by now (within 15 days), started its activities only couple of days back.
"We were busy, we could not start. We have extended the time. It will take some more days," the member secretary told bdnews24.com on Thursday.
Saying, "It's a huge task," he declined making further comments on the delay.
It is alleged that ICDDR,B wasted much of the fund by not following 'the sequence' of the construction work. They bought different items which were supposed to be bought at the end of the construction work. Those items had lost the guarantee period, it is charged.
Besides, some of its officials visited a number of countries like Japan, Germany, the UK and the USA with suppliers' money even before selection of bidders for buying necessary materials and equipment.
The committee will look into all these issues, according to the terms of reference (TOR) of the committee.
The TOR reads: "Whether logical sequence or critical paths were followed in implementation of the project or activities; for example whether things that could not be used before actual physical construction were procured and if so, on what basis?
"Whether officials of Finance and HR departments were sent abroad with suppliers fund even before selection of the bidders and has it compromised the procurement?"
The committee will also dig out other issues 'related to the implementation of the projects or activities disbursed to ICDDR,B from the government of Bangladesh'.
An ICDDR,B official told bdnews24.com that they were worried about the reputation of the centre, as it had not been 'well-managed' at least in the last five years.
He said once, the research organisation had brightened the image of Bangladesh across the globe.
The only centre of its kind in the developing countries, ICDDR,B was set up through an ordinance in 1978. The government is the largest donor of the centre which receives about Tk 100 million donations annually. It has been also given immunity from local taxes, rates and duties.
The centre also enjoys a legal mandate for movement of biological materials in and out of the country.
bdnews24.com/nih/nir/1945h