Published : 27 Dec 2015, 01:39 AM
Updated : 23 Apr 2022, 01:24 PM
The Japan International Cooperation Agency (JICA) recently wrote to Civil Aviation and Tourism Minister Rashed Khan Menon on the matter.
bdnews24.com has a copy of a letter by Mikio Hataeda, the Chief Representative at JICA's Bangladesh Office, in which it says that he wrote a letter to Menon in response to Menon’s request for a note on a meeting that they had had on Dec 15.
Hataeda said JICA received a master plan for the project from the Civil Aviation Authority of Bangladesh (CAAB) in November.
“We have carefully examined it and are now planning a supplemental survey at our own expense as a part of the preparation for our appraisal of the project,” he said.
He also said JICA would like to propose and discuss the scope and terms of reference of the survey with Menon’s ministry, the CAAB and other related authorities “as early as possible”.
Amid uncertainty over a lack of funds for the project, Menon had told bdnews24.com earlier in December that talks are being held with some Chinese companies about the project.
“We wanted to start the project in March or April, but it appears unlikely to me. It will be possible to start it by June or July,” he had said.
In May this year, the detailed proposal for expanding Dhaka airport, which includes erecting a third terminal, building a second runway, and undertaking other infrastructural developments, was forwarded to the prime minister’s office.
The proposal says the airport presently has the capacity to handle around eight million passengers annually. But it handled 6.7 million passengers in the first five months of this year alone.
With the volume of passengers increasing by 9.5% every year, the limit is expected to be crossed in 2018.
Prime Minister Sheikh Hasina told officials to treat the project as a priority. But the process was stalled because JICA, the South Korean government and the Kuwait Fund were not eager to finance the project.
According to a civil aviation ministry report in August, JICA had not responded to the Economic Relations Division’s (ERD) letter on funding for this project.
The project is not included in the eight projects to be funded by South Korea under its Economic Development Cooperation Fund (EDCF) Framework Arrangement either.
Its estimated cost exceeds Kuwait Fund’s ceiling for funding a project, says the report by the ministry.