Govt seeks Padma estimates

Three contractors have been asked to submit financial proposals for the construction of the Padma Bridge, said Communications Minister Obaidul Quader.

Staff Correspondent

bdnews24.com

Published : 11 Mar 2014, 02:26 PM

Updated : 08 Aug 2022, 06:34 PM

Letters sent to the primarily approved firms have asked them to place their financial estimates within Apr 3.

“Three international companies have sent their bids for bridge’s main infrastructure. Our technical committees evaluated them and approved the three companies,” Qauder told the press at Setu Bhaban, in Dhaka, on Tuesday.

“Now, we want them to give us their financial proposals. We have written to the three companies. They have to submit their papers within Apr 3.”

The government floated a global tender, after a long wait, in June last year for the construction of the bridge infrastructure.

The companies are China's Zhongtie Major Bridge Engineering Group Co. Ltd, India’s Daelim-L&T JV, and South Korea’s Samsung C&T Corp.

Image
File Photo

File Photo

The government has prepared its own estimate of the likely cost, said the minister. “We will compare it with the proposals the firms submit.” The original plan and design of the six-km bridge prepared by the World Bank remains unaltered, the minister said. The bridge will have both roads and railway tracks. The brigde, once built, will connect at least 21 southern districts with capital Dhaka. As Bangladesh’s biggest-ever infrastructural project, it is expected to increase economic growth by an additional 1.2 percent, the government said. The $2.91 billion project was supposed to be co-funded by the World Bank (WB), JICA, ADB and IDB but ran into trouble after the WB, the lead financer, raised the stink of ‘corruption’, and pulled out. However, the government, buoyed by rising foreign exchange reserves, decided to mobilise its own resources to fund the project.