Published : 20 Feb 2013, 09:46 AM
Updated : 09 Aug 2022, 10:16 AM
That includes two power generation projects . One is the 225MW dual fuel combined cycle power plant to reduce power crisis in Chittagong and the other is a grid interconnection between Bangladesh (Bheramara) and India (Baharampur) project (amended).
The projects will start in what would be the final fiscal year of the present Awami League-led government.
The approvals were made in NEC auditorium in Sher-e-Banlga Nagar in presence of Prime Minister Sheikh Hasina
The 225MW plant is expected to come up adjacent to Shikal Baha power station in Power Development Board land.
The Government says the plant will facilitate uninterrupted power in greater Chittagong.
Saudi Arabia, Kuwait, Abu Dhabi and Opaque Fund will contribute Tk 13.75 billion for the Tk 20 billion project.
The Bangladesh- India interconnection grid will be implemented under south Asian sub-regional cooperation.
The project cost increased to Tk 15.79 billion – almost a Tk 5 billion increase.
Planning Secretary Shafiqul Islam said the eight projects would cost a total Tk 78.82 billion.
Tk 48.14 billion is to be used from own funds while the rest is expected to be financed by aid money.
The other projects include upgrading of the Dhaka-Chittagong highway, Rangamati Science and Technology University, Mohammad Hanif underpass, ICT development, Kaliakoir High-tech park development and integrated irrigation development.