Semutang gas supply resumes after 15-hr hiatus
Bapex supply starts at 11.45, after unclear pipes forced it to stop around 8 pm Sunday
bdnews24.com News Service
bdnews24.com
Published :
05 Dec 2011, 11:48 AM
Updated :
10 Aug 2022, 05:54 PM
Chittagong, Dec 5 (bdnews24.com)— Bangladesh Petroleum Exploration and Production Company (Bapex) has resumed feeding Chittagong with gas from the Semutang field.
Gas flow resumed around Monday noon, slightly over 15 hours after it was shut down on Sunday due to a small operational snag. The supply was closed barely two hours after it began at 6.20 pm Sunday -- reportedly due to clogs in the Karnaphuli Gas Distribution Company Limited (KGDCL) supply lines.
"Gas supply resumed around 11.45 am (Monday) after the supply was closed and lines were cleaned at night. We hope the supply will not be interrupted," KGDCL managing director Sanowar Hossain Chowdhury told bdnews24.com.
At around 1.45 pm, Bapex general manager (production) and project director Mohammad Shahiduzzaman Khan said: "Gas flow through the pipes has been normal until now after it resumed. KGDCL officials are observing the flow at various points in the pipeline.
"There is still some water in the pipes, but the gas pressure can take care of it."
Shahiduzzaman had earlier said that Bapex had initiated supply, but it was stopped temporarily after "some problems developed due to the unclean supply line of KGDCL".
The problems arose since the KGDCL supply line was not cleared up even after the 'hydraulic test' was successfully carried out on November 21.
The Semutang gas field is estimated to supply 15-18 million units (1 cubic feet) gas every day – to be channeled only to the port city.
The gas field at Manikchharhi upazila of Khagrachharhi district was discovered in 1967. The then Pakistan Oil and Gas Development Company drilled four wells that were later abandoned.
Cairn Energy PLC drilled the fifth well in 1997 but abandoned the project after finding that the gas output was 'not feasible' for extraction.
Plans were undertaken to renovate the fifth well during the former caretaker government and the Executive Committee of the National Economic Council (ECNEC) on May 22, 2008 approved a proposal to allocate Tk 650 million for the project.
Mohammad Shahiduzzaman Khan said there are plans to drill another well in 2012 and that the four other wells are too old to extract gas.
KGDCL had finished construction of the 65-km pipeline in the middle of this year from the gas field, connecting with Chittagong at Fawzi flower Mill near Chittagong Cantonment.
bdnews24.com/cm/rn/std/1739h