Dhaka, Oct 5 (BDNEWS) – The government has formed a 25-member high-powered committee headed by Finance and Planning Minister M Saifur Rahman to formulate a plan and implement the mega Dhaka integrated flood control dam-cum-eastern bypass project.
"The committee was formed on September 28 as per the demands of the World Bank (WB), which was saying for long to set up a separate authority to implement the project," said a source in the Water Resources Ministry.
"After taking consent from the Finance Minister, who was made convenor of the committee, the Water Resources Ministry has issued a circular on September 28 mentioning the names of the members and terms and references of their tasks," the source told BDNEWS Wednesday.
The 25-member committee comprises five cabinet ministers, Mayor of Dhaka City Corporation (DCC), two state ministers, principal secretary to the Prime Minister, nine secretaries of different ministries and heads of RAJUK, Roads and Highways, Dhaka WASA, Local Government and Engineering Division, Forest and Environment Department, CEO of DCC and Water Development Board Director General, who has been made member-secretary.
About the committee's scope of work, the official circular said they would form a detail plan of the project mentioning scope of work, objectives, components, financing and implementation methodology of the project.
The committee will also recommend about the coordination during the implementation period of the project.
"This a very high profile committee and the members are too busy with their regular work, and that's why the ministry in its circular did not mention any timeframe for submission of the report," a competent source in the ministry told BDNEWS.
The Dhaka integrated flood control dam-cum-eastern bypass project is a multi-dimensional, complicated and expensive plan, he noted.
For the project's largeness and huge monetary involvement, Saifur Rahman earlier said, "We need to conduct more and more studies on whether we have capacity and other regulatory measures to carry out the work."
The project concept paper (PCP) of the project was approved at an ECNEC meeting on February 3, 1999. Water Development Board was named as the main implementing agency along with Roads and Highways, WASA, Dhaka City Corporation, Land Ministry, Department of Environment and RAJUK.
The cost of the project was estimated at TK 2,475.82 crore, of which, Tk 821.65 crore was supposed to be provided by development partners, particularly WB and the remaining Tk 1,654.16 crore by local sources.
About the estimation of the project cost, Saifur said the cost was projected in 1999 and it would not be less than Tk 3,000 crore in 2005.
BDNEWS/1743 hrs