Cabinet committee approves optical link installation project
The cabinet committee on purchase Monday approved the much-talked-about the purchase proposal for establishing Chittagong-Cox's Bazar 160-km-long optical link through sub-marine cable.
bdnews24.com News Service
bdnews24.com
Published :
04 Sep 2005, 06:00 PM
Updated :
18 Aug 2022, 11:58 AM
Dhaka, Sept 5 (BDNEWS) – The cabinet committee on purchase Monday approved the much-talked-about the purchase proposal for establishing Chittagong-Cox's Bazar 160-km-long optical link through sub-marine cable.
"Already, we are in behind to use of sub-marine cable," Finance and Planning Minister M Saifur Rahman told journalists after chairing a meeting of the cabinet committee on purchase.
Committee members and ministers and secretaries of the concerned ministries were present.
The cabinet committee also approved the Tk 25.49 crore digital telephone installation project in Chittagong, Khulna and Sylhet divisions, a water treatment plant in Chittagong and appointment of consultant for design and supervision of the Asian Development Bank-funded Emergency Damage Rehabilitation Assistance Project, 2004.
"Earlier, we had told the post and telecommunications ministry to float a re-tender for the optical link, as the ministry's evaluation process for selecting the bidders was not appropriate," Saifur said.
"This time, Tk 22 crore has been saved compared to earlier bidding," he told the reporters.
The purchase proposal for establishing Chittagong-Cox's Bazar optical link was sent back by the cabinet committee for several times on charges of manipulation and irregularities.
"The project cost is Tk 28.41 crore and we expect to launch the sub-marine cable by December this year," Hasan Mansur, Secretary of the T&T Ministry, told the reporters after the meeting.
Hesfibel of Turkey got the work as the lowest bidder, he said, adding: After approval of the Prime Minister's Office, we will issue the work order.
A technical committee evaluated the tender documents and selected Hesfibel as the lowest bidder out of seven as per the Public Procurement Regulations, Hasan Mansur said.
Nortel of Canada would provide equipment for the project, he noted.
"We will take just four months to complete the work of the project," he said. "We are hopeful to switch on the function by December."
BDNEWS/1724 hrs