Dinajpur, Oct 30 (BDNEWS) – The first unit of the 250-megawatt Barapukuria thermal power plant, country's first and only coal-fired plant, goes into operation in November, officials said.
The unit will generate 125 MW of electricity.
The second 125-MW unit will start generating electricity in February next year, they added.
Bangladesh Power Development Board (BPDB) has been implementing the project at a cost of Tk 1,660 crore.
Officials said the coal firing at the first unit would take place on November 7 followed by synchronisation of machinery on November 15.
Later the test run will begin, officials told State Minister for Power Iqbal Hassan Mahmood when he visited the plant on Saturday.
Engineers informed the minister that progress in implementation of the project was 90 percent so far.
Mahmood asked the engineers and officials concerned to implement the project on time to resolve the longstanding low-voltage problem in the northern region of the country.
The minister was accompanied by Abdul Matin, Member (Generation) of the Power Development Board (PDB), and Project Director Fazlul Haq.
Prime Minister Khaleda Zia attended the ground breaking ceremony of the power plant, beside Barapukuria coalmine of Petrobangla, the state-run oil, gas and mineral corporation, on April 23, 2003.
The plant is being constructed with suppliers' credit on 300 acres of land. The CMC, SEC and SEEC are cooperating.
Officials said foreign exchange worth US$ 200 crore will be saved as the plant will use coal of the Barapukuria mine instead of imported oil over 30 years.
Some 2,000 skilled and unskilled workers have been employed for implementation of the project. The plant will directly employ 500 people when it goes into operation.
BDNEWS/1511 hrs.