Barapukuria coal output set to double
A new method will be used from March 16 to increase production from Barapukuria coal mine in Dinajpur, a top mining official tells Aminur Rahman Rasel
bdnews24.com News Service
bdnews24.com
Published :
04 Mar 2012, 07:59 AM
Updated :
09 Aug 2022, 03:30 PM
Aminur Rahman Rasel
Energy Sector Correspondent
bdnews24.com
Dhaka, Mar 4 (bdnews24.com)—Miners will adopt a new method from Mar 16 to double coal production from the second slice of the mine at Barapukuria in Dinajpur.
Mohammad Kamruzzaman, managing director of the Barapukuria Coal Mining Company Limited (BCMCL), said on Saturday that the Long Wall Top Coal Caving (LTCC) method will allow them to lift pieces of coal with six-metre thickness from all sides of a slice.
The previous Longwall method only allowed extraction from the front side of a slice, he said.
LTCC is considered ideal for thick seams. In addition to proven safety advantages in the areas of face stability, operational control and management of spontaneous combustion the LTCC allows up to 80 percent recovery of additional coal that is usually not mined in conventional Longwall extraction.
"China, Russia and Australia are using LTCC method. Considering this, the method will be adopted with an aim to double the extraction," he added.
DEALS AND PAYMENTS
Operation in the mine is currently under suspension after the term of a deal between BCMCL and China National Import and Export Corporation (CMC)-led consortium with XMC to lift coal from the first slice ended on Aug 10 last year. The deal was signed in June 2005.
BCMCL signed another deal with the CMC-led consortium with XMC, after the first one expired.
The $200.97 million agreement is aimed at extracting around five million tonnes of coal from the second slice in 72 months, Kamruzzaman said. BCMCL will pay the money after selling the lifted coal, he added.
Extraction cost has been set at $56 a tonne in this fiscal year, which was $64.58 per tonne in 2010-11 fiscal, the MD said.
Though the consortium was supposed to extract 4.75 million tonnes of coal according to the first agreement, it lifted only 3.65 million tonnes, which is 0.099 million tonnes less than the target, he said.
At the beginning of the development of the mine in 1994, Chinese contractor CMC provided a supply loan of $109.235 million, he said.
The money was supposed to be paid back in 17 installments in eight years with five percent interest rate starting to be counted after six years of grace period, Kamruzzaman said.
CMC has already been repaid $118.341 million in 15 installments, he said. "The remaining $13.638 million will be paid back within September this year."
'$110 PER TONNE FOR PDB'
Kamruzzaman said Power Development Board (PDB) bought 80 percent of the coal extracted from the mine. Some brickfields and other private firms buy the rest, he said.
As the extraction is suspended now, BCMCL has stocked 120,000 tonnes of coal for the 250 megawatt thermal power plant of PDB adjacent to the mine, he said. The firm is not selling to others now to ensure power production.
PDB had been paying $84 a tonne while others pay $141, the mine MD said.
"The authorities have asked PDB to pay $110 per tonne after the extraction from the second slice starts," he said.
"It won't be possible to save the mine if they (PDB) want to buy coal at less than this ($110)," he added.
The mine has a reserve of 390 million tonnes of coal over a 6.68 square kilometers of area at Barapukuria of Parbatipur upazila, according to a 1985 survey by Geological Survey of Bangladesh.
bdnews24.com/arr/ost/jr/bd/1244h