4 gantry cranes commissioned in Ctg Port: BSAA protests new tariff
Country's premier seaport Chittagong entered the era of modernization with the installation of four sophisticated rail-mounted gantry cranes on Monday.
bdnews24.com News Service
bdnews24.com
Published :
29 Jan 2006, 06:00 PM
Updated :
17 Aug 2022, 05:45 PM
Chittagong, Jan 30 (BDNEWS) - Country's premier seaport Chittagong entered the era of modernization with the installation of four sophisticated rail-mounted gantry cranes on Monday.
Inaugurating the commissioning of the cranes Shipping Minister Lt. Col. (rtd) Akbar Hossain hoped that the container handling capacity of the Chittagong Port would greatly increase with the installation of these cranes. This would reduce time-lag of ships from seven days to two days, he said.
The Chittagong Port Authority (CPA) has already procured four rail-mounted quay gantry cranes at a total cost of Tk 120 crore from the Japanese company Mitsubishi.
A total of 138 out of 141 container handling equipment have been procured at a cost of Tk 330 crore to gear up container handling capacity in Chittagong port.
The Bangladesh Shipping Agents Association (BSAA) feared that the handling charge of a container would increase to nearly TK 30 crore per annum with the imposition of the new tariff.
The shipping minister said, though in the face of strong opposition they were compelled to reduce the handling tariff to half for next two months but BSAA leaders said they would stay away from using the gantry cranes for at least six months protesting the newly imposed tariff.
As a meeting held between Shipping minister and the BSAA leaders ended inclusively BSAA leaders boycotted the inaugural ceremony and later at a press conference demanded of the Prime Minister to withdraw the new tariff otherwise they threatened that they would not use the gantry cranes.
The inaugural function chaired by CPA chairman AMM Shahadat Hossain was addressed among others by Fisheries Minister Abdullah Al Noman , President of Chittagong Chamber of Commerce and Industry Saifuzzaman Chowdhury and T Shoji , General Manager of M/S Sumitomo Corporation.
Chittagong city mayor A B M Mohiuddin Chowdhury who was scheduled to attend the function as special guest was conspicuously absent.
Speaking on the occasion, the Shipping minister said all modern facilities would be provided in Chittagong port to cope with the global maritime trade .
The seven sisters of India have already expressed their keenness to use Chittagong port, Akbar pointed out.
The minister also said that the ongoing construction work of the New Mooring Container Terminal must be completed before end of the tenure of this government and Prime Minister Begum Khaleda Zia would inaugurate the terminal.
Fisheries Minister Abdullah Al Noman said development and modernization of Chittagong port are precondition of turning Chittagong into a commercial capital.
Noman said that a TK 1700 crore-development project is going on in Chittagong but admitted that desired development could not be achieved due to politics reasons.
CPA sources said, with the procurement of the cranes, the container handling capacity of the Chittagong Port is expected to increase by 30 per cent.
The total container handling capacity of the Chittagong Port will rise to six lakh after procurement of the said equipment.
BDNEWS/2004 hrs