WB wants transparency in implementation
Padma Bridge is a huge project and there should be transparency in its spending, says World Bank's country director in Bangladesh.
bdnews24.com News Service
bdnews24.com
Published :
13 Jan 2011, 11:29 AM
Updated :
10 Aug 2022, 04:12 PM
Dhaka, Jan 13 (bdnews24.com) – The World Bank has proposed the government to form a separate independent body to ensure transparency in financing the $2.9 billion Padma Bridge project.
The World Bank will provide $1.2 billion with further commitment of $300 million for the giant project.
"The people of Bangladesh have the right to know about the project and we ask the government to adhere to right to information act in this regard," WB Bangladesh chief Allen Goldstein told a pres conference on the project on Thursday.
"There should be a project integrity advisor who will directly report to the prime minister and a two-tier grievance redress mechanism," she said.
She said the World Bank has trust in the government, "but it's a huge project and there should be a transparency mechanism in spending system so that it remains above any controversy."
"Given the importance and scope of this operation for Bangladesh, the World Bank wants to ensure the highest quality standards from start to finish of the bridge," she added.
Economic Relations Division additional secretary Arastoo Khan said it is a good thing to form a separate committee. "The stakeholders, including suppliers and contractors, will be assured that that transparency is there," he said.
Khan said, "Nowadays, there is a practice that renowned independent organisation like Transparency International or NGOs are invited when tenders are opened to avoid controversy."
"The negotiation with the WB has been concluded and after the approval by its board in February, the government and the lending agency will formally sign an agreement to make the money available," Khan told reporters.
The bridge, he said, has three aspects -– social, economical and regional connectivity.
"The country will be benefited economically when national integration will be strengthened after the construction of the bridge and," he said.
The GDP will grow by 0.6 percentage point after the construction and poverty will be reduced by 1 percent in the country's southwestern region, he said.
"Regional connectivity will get a boost as Asian Highway will use the bridge and it will reduce burden on Chittagong port," he said adding, "Mongla port will be benefited from the bridge, too."
The government has attached top most priority to the construction of the bridge within the tenure of the current regime.
The bridge will connect the southwest region with the rest of the country and Dhaka will get closer to nearly all destinations by about 100 kilometres.
It will be a 6.15-kilometre long double-deck steel truss four-lane bridge, and a single rail track will be there on the bottom deck.
The government has so far compensated 1400 households out of the total affected 13500 households. Some 1200 hectares of land will be acquired for the project.
bdnews24.com/ssz/mr/1720h