Tullow discovers half TCF gas in Bhangura
Tullow Oil Plc has discovered about half trillion cubic feet (TCF) of gas at Bhangura in the country's gas block 9.
bdnews24.com News Service
bdnews24.com
Published :
06 Mar 2005, 06:00 PM
Updated :
17 Aug 2022, 08:17 PM
Advisory: With photo
Dhaka, March 7 (BDNEWS) – Tullow Oil Plc has discovered about half trillion cubic feet (TCF) of gas at Bhangura in the country's gas block 9.
However, the Irish oil company does not want to make the commercial discovery announcement right at this moment.
"It wants to make the announcement after test production for six months from November or December this year," said an official at Petrobangla.
The Tullow Monday made a presentation before the officials of Petrobangla, the state-run oil, gas and mineral corporation.
It also approached to set up pipeline and develop a processing plant for gas production from Bhangura of Debidwar in Comilla.
If the proposal is accepted, Tullow will produce 40-45 MMCFD (million cubic feet per day) from the field.
Petrobangla signed a production sharing contract (PSC) with Tullow, ChevronTexaco and BAPEX for the block on April 11, 2001.
Under the PSC, the Tullow as operator of the block had an abortive drilling at Lalmai in Comilla.
Later, it conducted drilling in Bhangura and found presence of gas.
After many tests, Tullow found six prospective zones. Gas was detected in five of the zones.
After conducting tests at D and E layers, Tullow informed that the gas reserve in Bhangura is 457 billion cubic feet (BCF).
The Tullow flowed gas at a rate of 54 MMCFD in D layer and 24 MMCFD in E layer.
BDNEWS/1955 hrs