Published : 08 Jul 2017, 09:05 PM
Updated : 19 Oct 2022, 03:40 PM
The Chouhali Upazila Protection Dam was being built for the last two years under the supervision of Bangladesh Water Development Board or BWDB, but it repeatedly suffered setbacks and is unlikely to be completed by the July deadline.
The two-year project was supposed to be completed by July this year, but between May 2 and Jul 3, the dam collapsed six times in different places.
A 60 to 70-metre segment of the dam was washed away on Friday as the water level in Jamuna River continued to rise for past several weeks.
The river was flowing 15cm above the danger mark Saturday morning.
The first damage on the embankment was reported in early May when a 100-metre section of the dam was washed away by the rushing water of the mighty Jamuna. Similar collapses were reported in June and July.The locals held the contractors and the BWDB officials responsible for the poor construction works.
When contacted, BWDB executive engineer in Tangail, Shajahan Siraj told bdnews24.com that “the cracks occurred for the sixth time due the rising water level in Jamuna”.
“The soil in these areas is very corrosive. The swirling water caused the erosion even quicker but there is nothing to be worried about,” he added.
A committee has been formed with two water experts to look into the matter, he also said.