Published :
23 May 2013, 09:05 AM
Updated :
09 Aug 2022, 10:42 AM
Flights have not been operating for nine hours a day from Dec 1 for the repairs to take place. This schedule ends on May 30.
Civil Aviation Authority Director (flight safety and regulation) Wing Commander Nazmul Alam confirmed that flights will remain closed from 12 midnight until 4:30am in the morning everyday from Jun 1 to Aug 30.
However, if more time is needed for the repairs, the four-hour flight embargo can be extended for a while, he said.
“Repair of the runway is complete, but work on illumination is not yet complete, which is why we still need some time to allow for round-the-clock flight operation ," Alam said.
Meanwhile, works to upgrade the taxiway began Aug 1 last year and is scheduled to be completed until June 2014.
Shahjalal is the major airport of the country with 42 carriers and three cargo planes landing and taking off everyday on an average.