Dhaka, June 27 (bdnews24.com)—The ordinance on land acquisition for the Dhaka Elevated Expressway has been passed in parliament, with the provision to remove any obstacle to acquire land for the project, the first of its kind in the country.
Land minister Rezaul Karim Hira placed the bill on Monday morning where it was passed through voice votes.
The law will come into effect from May 12 this year.
As per the decree, the land acquired and to be acquired for the project will be considered to have been 'needed for public interest.'
Compensation will not be given to anybody if they build any structure against public interest on the acquired land and nobody can file a suit with any court against the action taken under the ordinance.
The Dhaka Elevated Expressway Project (Land Acquisition) Ordinance, 2011 was promulgated on May 12 when the parliament was not in session.
Prime minister Sheikh Hasina inaugurated the project on April 30.
Hira said the law was enacted so that no one could realise compensation illegally from the government by erecting any structure on the acquired land.
He said the trend was visible these days among some people with ill-motive. "A good amount of money will have to be spent to acquire the land if the practice can't be prevented."
The bill stipulates that compensation would be determined through video footages of the land taken earlier.
In case of rejection of an appeal against the acquisition, the plaintiff has to remove property and infrastructure at his/her own cost.
Three corrections, suggested by ruling MP A K M Mozammel and independent MP Fazlul Azim, were accepted on the bill
According to Article (2) of clause 93 of the constitution, the government must place the ordinance before parliament in the next session.
The government on Jan 19 signed a deal with Italian-Thai Development Public to build the expressway in Dhaka.
The four-lane 26-kilometre elevated expressway will link Shahjalal International Airport to Kutubkhali on the Dhaka-Chittagong highway via Kuril, Banani, Mohakhali, Tejgaon, Satrasta, Moghbazar, Kamlapur, Khilgaon and Golapbagh.
The final tender for the Tk 140 billion project was floated on Nov 23 last year.
bdnews24.com/sum/pks/tk/1307h.