Published : 10 Feb 2014, 07:05 PM
Updated : 08 Aug 2022, 06:28 PM
The government has been given two weeks to reply.
A High Court bench comprising Justice Mirza Hussain Haider and Justice Muhammad Khurshid Alam Sarker passed the order on Monday after the primary hearing on a writ petition jointly filed by three citizens of Moheshkhali.
The Power, Energy and Mineral Resources Secretary, Environment and Forests Secretary, Land Secretary, Director General of the Department of Environment (DoE), Chairman of Bangladesh Power Development Board, Managing Director and Secretary of Coal Power Generation Company Bangladesh Limited (CPGCBL), Deputy Commissioner and Police Superintendent of Cox’s Bazar, Moheshkhali Upazila Executive Officer (UNO) and Officer-in-Charge of the Moheshkhali Police Station have been made respondents.
The court in its ruling asked the respondents to explain why they should not be directed not to install the coal-fired power plant considering its harmful impacts/effects on the area’s natural resources, biodiversity, water bodies, very fertile land, and the health of the inhabitants.
Barrister Sheikh Mohammad Zakir Hossain, assisted by Advocate Mirza Al Mahmud and JR Khan Robbin, argued for the petitioners.
Three people – Mohammad Rafiqul Islam, Abul Hashem and Altaf Hossain – had filed the petition on October 6.
The High Court ruling comes at a time when the government is trying to increase electricity generation by using coal.
The government plans to achieve 20,000 megawatt power generation capacity by 2021 – mainly on the back of fuel diversity and harnessing of renewable energy resources.
It also plans to boost power-generation capacity by reducing reliance on natural gas and increasing coal-based power to 53 percent within that year.
Currently, about 75 percent of Bangladesh's power is being generated by gas-driven plants, while less than three percent comes from coal-based plants.
The government laid the foundation of the Indo-Bangla Rampal coal-fired power plant in Oct amid a loud outcry against its possible impact on the fragile Sunderbans ecology.
The Rampal plant is designed to have a generation capacity of 1320 MW but environmentalists fear it would destroy the world’s largest mangrove forest.
Besides, experts differ on the extraction coal from the country’s coal fields. Many favour open-pit mining to reduce costs, while others favour the underground pit mining to minimise impacts on the environment.
Last week, Prime Minister Sheikh Hasina at a programme stressed the need to protect arable land and directed the energy ministry to wait for 'new technology' before going for coal extraction.
She said that the government decided not to go for coal extraction at any new field and stressed that food security was its first priority.