Govt fails to achieve first target to raise power generation for next summer
With the Power Development Board (PDB) chalking out a contingency plan to raise electricity generation in the private sector to face the coming summer demand, it failed to maintain the deadline even in beginning the preparatory work of the programme.
bdnews24.com News Service
bdnews24.com
Published :
17 Nov 2005, 06:00 PM
Updated :
18 Aug 2022, 12:16 PM
Dhaka, Nov 18 (BDNEWS) – With the Power Development Board (PDB) chalking out a contingency plan to raise electricity generation in the private sector to face the coming summer demand, it failed to maintain the deadline even in beginning the preparatory work of the programme.
The PDB had set November 15 to start selling tender documents for skid and barge mounted power plants for raising the generation by 360 megawatt in next eight months, but the proposal is yet to get nod from the Power Division and the Prime Minister's Office.
"Even primary discussion has not taken place," said a senior concerned official.
With 800 MW current deficit of electricity, the PDB has been apprehending that the shortage will stand at over 1,000 MW in the summer when irrigation will start.
Against the present daily demand of 4,400 MW the generation is 3,600 MW. With a rise of generation by another 300 MW in next few months, the total generation will stand at 3,900 MW in the summer when the demand will be 4,900 MW.
"In this situation, the PDB had planned to raise the generation by another 360 MW by establishing skid and barge mounted power plants to take the total generation to over 4,200 MW," said the official.
The plan shows that 160 MW will come from skid mounted plants at Kumargaon in Sylhet, Shahjibazar, Bogra, Katakhali in Rajshahi and Thakurgaon while 200 MW from barge mounted plants planned at Fenchuganj, Khulna and Shikalbaha.
Officials said after necessary bidding procedures and approval from the proper authorities, the PDB had planned to issue letter of intent by January 15 this year for setting up the skid mounted plants in 90-120 days and barge mounted plants in 150-180 days.
"Now it seems that implementation of the projects will not be possible at targeted time indicating that the country will experience the worst summer immediately before the 4-party government leaves power on completion of its tenure," said another senior official.
BDNEWS/1811 hrs