  • Bangladesh
  • Sport
  • Technology
  • Opinion
  • Politics
bdnews24.com
বাংলা
  • World Cup
  • World
  • Opinion
  • Entertainment
  • Lifestyle
  • Economy
  • Business
  • Cricket
  • Recent
bdnews24.com
Home
  • Bangladesh
  • Politics
  • Campus
  • Education
  • Media
  • Environment
  • Health
  • Fashion
  • People
  • Automobile
  • Aviation
  • World
  • Science
Sport
  • Sport
  • Cricket
World
  • Middle East
  • Europe
  • Neighbours
Business &
Economy
  • Business
  • Economy
  • Budget 2025-26
Features
  • Opinion
  • Technology
  • Lifestyle
  • Entertainment
  • Hello
  • Stripe
Others
  • Photos
  • Tube
  • Mobile
  • Bangladesh

Dhaka Metrorail to carry 60,000 people per hour

Each of the 56 trains in the proposed Metrorail mass transit system will carry 1,800 passengers and will run every four minutes, or 60,000 people every hour.

Shamim Ahmed

bdnews24.com

Published : 23 Sep 2014, 12:05 AM

Updated : 23 Sep 2014, 12:05 AM

The tracks will run above the middle of roads, starting from Uttara and ending at Motijheel. Each train will take less than 40 minutes to run the whole distance.

Speaking to bdnews24.com, Metrorail Project Director Md Mofazzal Hossain said each train will have six coaches.

“Assuming there will be eight people per square metre at the busiest hour, each train will be able to carry 1,800 people,” he said.

Of the total cost of Tk 220 billion, JICA, the agency that coordinates development assistance on behalf of the government of Japan, will provide Tk 165.95 billion. The Bangladesh government will take care of the remaining Tk 53.90 billion.

The Metrorail’s detailed design will be finalised in July next year, he said. The project will be completed by 2019.

Call for eight bids for construction

The Metrorail Project is preparing to invite eight bids for six construction packages.

“Primarily we’ll invite the bids for the construction of the Metrorail Depot at Uttara Third Phase in December,” Hossain said.

“From early next year you’ll see the construction work begin.”
“Serially we’ll invite four bids for the bridge and the stations, one for the rail coach purchase and another for the electrical mechanical works,” he said.
The bidding process will continue until 2017.
An electric train has been introduced in India’s Mumbai this year. The one in Dhaka is being built in the same model. The Metrorail will run over the middle of the road.
Its bridge will be about two-storey high and the stations will have two floors.
“We’ll build this 21 kilometres long bridge first and then lay tracks on it,” Hossain said.
“The first floor of the stations will have automated doors and ticket booths,” he said.
The stations will be 180 metres long. There will be no air conditioning at the stations.
During the construction project five temporary construction yards will be built and the work will be done from 11pm to 6am.
The cabinet on principle approved a law related to land acquisition for the Metrorail on Apr 28.
ECNEC approved the project in 2012.
The 16 Metrorail stations will be Uttara (North), Uttara (Centre), Uttara (South), Pallabi, IMT, Mirpur 10, Kaziparha, Taltala, Agargaon, Bijoy Sarani, Farmgate, Sonargaon, National Museum, Doel Chattar, Bangabandhu National Stadium and Bangladesh Bank.
Follow bdnews24.com on Google News
Related Stories
Ctg battered by heaviest rain in 42 years
Ctg battered by heaviest rain in 42 years
Waterlogging in Ctg after 330mm of rain
Waterlogging in Ctg after 330mm of rain
Bangladesh police ready for Haiti challenge: minister to UN
Bangladesh police ready for Haiti challenge: minister to UN
Parjatak Express stuck in Ctg due to water on rail line
Parjatak Express stuck in Ctg due to water on rail line
Read More
Deal with Iran is over: Trump
Deal with Iran is over: Trump
Iran truce deal over: Trump
Iran truce deal over: Trump
Ryanair loses appeal on Italy's COVID aid to airlines
Ryanair loses appeal on Italy's COVID aid to airlines
Referees match players stride for stride
Referees match players stride for stride
Read More
Opinion

Afiq Fitri Alias

Iran $300bn rebuild fund risks familiar fate

Iran $300bn rebuild fund risks familiar fate

Jibran Saaed

Questions hang over Jamaat's political strategy

Questions hang over Jamaat's political strategy

Shakila Mim

The greatest love triangle in football

The greatest love triangle in football

Towheed Feroze

WC 2026: Three cheers for the Asian sides!

WC 2026: Three cheers for the Asian sides!
Read More
Editor-in-Chief and Publisher: Toufique Imrose Khalidi
News
  • Home
  • Bangladesh
  • Business
  • Politics
  • Economy
  • World
  • Technology
  • Science
  • Environment
  • Health
Op/Ed
  • 1971
  • Achievement
  • CHT
  • Corruption
  • Culture
  • Democracy
Social
  • Facebook
  • Twitter
  • Instagram
  • Youtube
  • WhatsApp
Features
  • Tech
  • Lifestyle
  • Entertainment
Others
  • Stripe
  • Hello
  • Mobile
Sport
  • Sport
  • Cricket
Follow us
  • Disclaimer & Privacy Policy
  • About Us
  • Contact Us

Copyright © 2026, bdnews24