November 23, 2026

Dhaka court orders ACC to reinvestigate case on Rana Plaza irregularities

Errors detected in the chargesheet by the Anti Corruption Commission (ACC) in a case over irregularities during the construction of the ill-fated Rana Plaza complex have moved a Dhaka court into ordering a reinvestigation.

Court Correspondent

bdnews24.com

Published : 06 Mar 2016, 09:51 PM

Updated : 11 Apr 2022, 09:42 PM

Judge M Atwar Rahman of the Dhaka Divisional Special Judge Court issued the order on Sunday after a hearing to frame charges in the case, filed over anomalies in the building’s design plan and a violation of building codes.

State counsel Shahin Ahmed Khan told bdnews24.com that, according to the court, the investigation missed information regarding the irregularities in the approval and construction of Rana Plaza.

The chargesheet also did not implicate the people who were involved.

“After going through the case files, the court, after taking into consideration public interest and sensitivities involved in it, decided that the case needed reinvestigation.”

The court then ordered the ACC to submit the new report by May 8.

The Rana Plaza collapse, one of the worst industrial accidents in the country, occurred on Apr 24 in 2013 at Savar on the outskirts of the capital.

The accident claimed at least 1,135 lives, mostly workers of five readymade garment factories housed in the building. More than a thousand workers were injured in the collapse.

The case was filed with Savar Police on Jun 15, 2014, against 17 people with charges of anomalies in the construction of the building.

The case led to a nationwide furore as it did not name the building’s owner, Sohel Rana, among the accused.

In July the same year, the ACC submitted the chargesheet against 18 people, including Rana.

According to the chargesheet, Savar Municipality approved Rana Plaza’s six-storied shopping complex design on Apr 10, 2006. In January 2008, approval for another four floors was sought from the authorities.

The municipality approved the design of a 10-storey building, burying the previous approval files. It also approved the five garment factories, even though the building had previously been approved for a shopping complex.

In 2014, case supervisor and ACC Director Tahidul Islam told bdnews24.com, “We have found that no rules were met during Rana Plaza’s construction. The building also violated the design plan.

“The building was in Rana’s parents’ name but he was behind the persuasion, financial irregularities and corruption it took to make it.”

According to the investigation, Rana had financial transactions through 23 accounts in different banks. He owns a five-storey residential building at Savar, a two-storey building and two brick kilns in Manikganj’s Singair.

Rana was arrested at the Benapole border in Jessore four days after the building collapsed.