The implementation work of the proposed Bhasantek sub-urban project on 150 bighas of land at Mirpur in the capital has been suspended.
bdnews24.com News Service
bdnews24.com
Published :
11 Oct 2005, 06:00 PM
Updated :
18 Aug 2022, 12:08 PM
Dhaka, Oct 12 (BDNEWS)- The implementation work of the proposed Bhasantek sub-urban project on 150 bighas of land at Mirpur in the capital has been suspended.
Chairman and Managing Director of North-South Property Development Ltd (NSPDL), the authorized constructing firm of the government, Abdur Rahim at a press conference in Dhaka Wednesday alleged that the project is hanging up due to complexity of the Land Ministry.
NSPDL chairman said his firm invested about 50 crore taka in a year for the development work of the project under an agreement signed with the government in September 29, 2003.
"According to the condition of the agreement, selling applications among the interested persons started, but the Ministry stopped the selling and interfered it violating the conditions of the agreement", he added.
Abdur Rahim said his firm would finally close up the implementation work of the project if the complexity were not removed within a month.
He said two category flats would be built under the project that is expected to be to the tune of Tk 400 crore investment.
In the project, around 15,024 flats are scheduled to be constructed for slum dwellers and low-income people.
Under the project, 215 square feet flat would be provided to slum dwellers at a cost of Tk two lakh per flat while 395 square feet flat would be for low-income people at a cost of Tk 3,90,000.
Project Director Sirajul Islam, Chief Engineer Habib Mostafa, Public Relations Officer Ismail Hossain were present at the press conference.